Engineering Wonders of the World
Volume I
År: 1945
Serie: Engineering Wonders of the World
Sider: 448
UDK: 600 Eng -gl.
Søgning i bogen
Den bedste måde at søge i bogen er ved at downloade PDF'en og søge i den.
Derved får du fremhævet ordene visuelt direkte på billedet af siden.
Digitaliseret bog
Bogens tekst er maskinlæst, så der kan være en del fejl og mangler.
THE RIVER TUNNELS
finished, its slope was lumpy, irregular, and
in places too steep.
Now, the design did not include a thick
concrete lining as in the Pennsylvania tubes,
and the leeway for divergence from true line
was small. In short, the conditions were such
that it was necessary to make an attempt to
straighten the tubes. Mr. W. I. Aims was the
contractor’s engineer.
An ingenious plan of doing this was schemed
out and successfully executed. It consisted
in cutting away, as it were, the humps of the
OF NEW YORK CITY. 121
been excavated deep enough (only a few feet
in the worst case), a strong concrete bottom,
reinforced with steel rods, was put into the
desired new outline.
A more serious difficulty was encountered
at one point where it was desired to raise
the top for a short distance. This was accom-
plished by forcing the plates upward (after
unbolting) by means of powerful jacks, and
simultaneously loosening and washing out the
sand above by water streams and stirring rods
through holes in the plate.
TUNNEL WITH CONCRETE-FILLED FOUNDATION PILES.
TUNNEL IN ROCK AND SHIELD-DRIVEN PORTIONS.
Fig. 23.—CROSS-SECTION OF BATTERY
Fig. 24.—SECTIONS OF THE STEINWAY
bottom down to a new bottom line corre-
sponding to the parts which had sagged most.
This necessarily produced an irregular and
varying outline of tunnel ; but that was no
disadvantage, as the reconstructed tunnel
could be lined with a thin layer of concrete
so distributed as to produce a fairly regular
outline all along.
The process of cutting down the bottom
was briefly this: A bottom segment of
lining having been unbolted and broken to
pieces by heavy hammers, the air pressure
was raised to balance exactly the soil pressure
at that point. Then the bottom plate was
taken oat, and, under the perfectly balancing
air pressure, the soil could be dug away
without dr nger. The whole length of a hump
was treated in this way, and after the soil had.
Finally, another remarkable thing was done
in this tunnel. A belief gained ground that
the tunnel would be unstable, being in quick-
sand, and it was decided to sink foundation
piles under it, to give a firm support. The
plan was carried out, several hundred feet of
length being thus underpinned. Bottom plates
were broken out just as for reconstruction,
and then large vertical iron pipes were
“ jetted ” down—that is, were pressed down
by jacks while a stream of water, forced
through a small pipe attached to the
bottom of the pile, washed away the sand
below it. When the pile finally rested on
rock or firm ground, it was cleaned out
and filled with concrete, and then a con-
crete “ cradle ” was built around the top
of the pile to support the tunnel. Two such