Engineering Wonders of the World
Volume I
År: 1945
Serie: Engineering Wonders of the World
Sider: 448
UDK: 600 Eng -gl.
Søgning i bogen
Den bedste måde at søge i bogen er ved at downloade PDF'en og søge i den.
Derved får du fremhævet ordene visuelt direkte på billedet af siden.
Digitaliseret bog
Bogens tekst er maskinlæst, så der kan være en del fejl og mangler.
DOCKS.
the water is pumped out of the dock. As she
rests on the blocks men prop her up with tim-
ber shores, whose lower ends are supported by
the steps or 11 altars ” in the side-walls. When
the repairs, etc., are completed, the water is
let into the dock again, and the vessel is floated
out at full tide. In some cases there is no
need to wait for the flood in order to dock
or undock a ship. If a dry dock is access-
ible from a wet dock, the work can be done
at any time. The emptying of a large dry
dock looks a much more serious operation than
it really is. The big graving dock at Govan
holds 13,762,500 gallons, yet at the very first
trial it was pumped dry in an hour and forty
minutes. On the second trial the work was
done in an hour and a half—about 700 tons
being discharged per minute. The dock is
divided into two sections. If there had been
a ship displacing 10,000 tons in the larger of
these sections, the time would have been re-
duced to less than 35 minutes. The machinery
used consists of two 60-inch centrifugal pumps,
each driven by a pair of vertical direct-acting
steam engines with cylinders of 28 inches in
diameter and a stroke of 24 inches.
The floor of a graving dock slopes down on
each side from the centre, to allow the water
to find its way by gravitation to the main
culverts underneath, whence it is pumped out.
The capacity of a dry dock
is determined both by the
width of the entrance to it
and the depth of water over
the sill against
which the
gates close.
Although the largest of the
dry docks at Tilbury is 875
feet long, and has a depth
over the sills of 31J feet at
high water of neap tides, it is
inaccessible to a Dreadnought
or a Lusitania because of its
entrance being not more
Large
Dry Docks.
than 70 feet wide. Cases of the same kind
are to be found in other ports, because in
the past ten years ships have developed
in beam to an unexpected extent. The
majority of these long but inadequately wide
docks have been subdivided by placing other
gates at some convenient point between the
entrance and tho end of the dock. In one of the
docks at Belfast there are two pairs of extra
gates and three sub-divisions. Where this
practice is followed, the docking of two or
three vessels in the one dock independently
of each other becomes possible, with obvious
limitations. A vessel or vessels in the inner
berth or berths could not be undocked with-
out undocking the vessel or vessels in the outer
berth or berths.
The following table gives particulars of some
of the most important dry docks :—
Dock. Length. Width at Entrance. Depth over Sills.
Canada Dock, Liverpool 925| ft. 94 ft. 29 ft.
Tranmere, on the Mersey 900 ft. 95 ft. 33 ft.
Brocklebank, Liverpool 804 ft. 96 ft. 31 ft. 10 in.
Trafalgar, Southampton 860 ft. 90 ft. 33 ft.
No. 10, Devonport (double)....459&250ft, . 95 ft. 47| ft-
Kiel 570 ft. 94 ft. —
Kaiser, Bremerhaven 741| ft. 98| ft. 35| ft.
Wilhelmshaven (No. 4) 580 ft. 101 ft. —
Havre 787 ft. t 98| ft. 29| ft.
Spezia G87 ft. 105| ft. 33 ft.
Nagasaki 714 ft. 96| ft. 34J ft.
Charlestown, Boston, U.S.A. 718| ft. 112 ft. 30 ft.
These figures indicate the magnitude of the
(Photo, S. Cribb.)
THE TRAFALGAR DOCK, SOUTHAMPTON.