Engineering Wonders of the World
Volume I
År: 1945
Serie: Engineering Wonders of the World
Sider: 448
UDK: 600 Eng -gl.
Søgning i bogen
Den bedste måde at søge i bogen er ved at downloade PDF'en og søge i den.
Derved får du fremhævet ordene visuelt direkte på billedet af siden.
Digitaliseret bog
Bogens tekst er maskinlæst, så der kan være en del fejl og mangler.
THE NEW YORK SUBWAY. 347
Fig. 5.—EXCAVATION IN ROCK UNDER A BUSY
STREET.
Only half the full width excavated at once.
the soil to be excavated. Narrow transverse
trenches were first dug under the tracks, at
intervals of 40 feet, down to the Subway floor
level. In these trenches, on a footing of
concrete, were erected frames of timber posts
and bracing, carrying at street-level on either
side of the tracks a pair of longitudinal steel
girders (see sketch, Fig. 6). The girders sup-
ported hangers, which held
up short transverse beams
drawn in through drifts
under the tracks. Then
wedges were driven be-
tween these beams and
the track structure, so as
to throw the weight of the latter entirely
on to the system of beams, girders, and
trestles.
The excavating and building operations
were thus carried out; in some cases first on
one side to completion, then on the other ; in
other cases on the full width simultaneously.
Cableways were used for hoisting out the
excavated earth, or rock.
Broadway in its upper part is unusually
wide, and has a parked strip, 22 feet wide,
extending along the middle, between the
car tracks. The Subway was to extend
Fig. 6.
about 10 feet beyond either track, leaving
some width of undisturbed
pavement along the
Rock lay from 5 to
below the surface on
this required blasting.
The contractor’s method
carve away the parked strip
only, as he had also to undermine the car
tracks laterally, it was necessary to support
these tracks by timbering. For this purpose
a very short length, say 40 feet, was the
basis of operations. Strong timber or steel
trusses were set longitudinally on either side
of each track over the 40 feet working length,
and excavation progressed on this length, from
the middle toward the sides. As soon as a
cavity had been made under the track at one
point, a crossbeam was pushed through, hung
by bolts to the trusses, and drawn up to a
bearing against the track. Thus in time the
whole 40 feet length of track was carried by
the trusses, and the soil could be taken out
to the bottom for the full width required
(Fig 7). Then posts were set up under the
curbs. 3. Along the
Boulevard.
10 feet
much.
of this length. ;
was simply to
and dig down ;
Fig. 7.—timber truss supports used along
BROADWAY.
track, and the load transferred to them from
the trusses. The trusses being thus relieved,
they could bo shifted along to the next length,
and the operation repeated. In Fig. 8 several
sets of these trusses are seen in use.
The posts continued to support the tracks
during the erection of the steelwork and con-
crete, until other supports could be provided
on the first of the roof beams ; and, finally,
stone filling was laid over the finished roof
as a new bedding for the track. 1
While the preceding is a fair picture of how
the problem of building the Subway was