Engineering Wonders of the World
Volume I
Forfatter: Archibald Williams
År: 1945
Serie: Engineering Wonders of the World
Forlag: Thomas Nelson and Sons
Sted: London, Edinburgh, Dublin and New York
Sider: 456
UDK: 600 eng - gl.
Volume I with 520 Illustrations, Maps and Diagrams
Søgning i bogen
Den bedste måde at søge i bogen er ved at downloade PDF'en og søge i den.
Derved får du fremhævet ordene visuelt direkte på billedet af siden.
Digitaliseret bog
Bogens tekst er maskinlæst, så der kan være en del fejl og mangler.
THE STORY OF THE SEVERN TUNNEL.
87
than a couple of miles, and completely filled
the great cutting of the Gloucestershire ap-
proach. Had a heading existed right through
from the Marsh Shaft nothing could have
saved the men below.
As it was, the position of affairs looked
deplorable enough—the tunnel partly, and the
cutting quite, full of water, great damage
done, and long delay inevitable. The con-
tractor was already some £100,000 out of
pocket over the contract.
The worst had been passed, nevertheless.
There were, indeed, periodical breakdowns of
the pumps and minor troubles, but work went
ahead so steadily that by the end of 1883 the
larger part of the tunnel lining had been put in.
The method of tunnelling employed con-
sisted of driving a heading, or gallery, at the
level of the bottom of the tunnel, making
“ break ups ” from this at
Method of short intervals, and from the
Tunnelling- top of these working top
employed. headings in both directions,
at the level of the crown.
These upper headings were enlarged and tim-
bered where necessary ; then the ground
between them and the lower headings was
broken away vertically ; and finally the two big
side benches of stuff were removed. When a
length of tunnel had been thus enlarged to full
section and timbered, the masons got to
work, and under cover of the wooden cage
built first the invert and then the side walls.
Semicircular wooden “ centres ” were then
arranged athwart the upper part of the cavity,
parallel to one another, and from 3 to 4 feet
apart. Beginning at the top of the side walls,
the masons laid a “ lagging ” of stout boards
3 inches thick horizontally along the outside
of the centres, which it touched, and con-
tinued the brickwork upwards in courses, care-
fully filling in all spaces between the brick-
work and the ground. Fresh laggings were
added on either side as required, and the
brickwork brought up to the crown, or top-
most part of the arch. For the last 18 inches
the mason used short laggings resting on only
two centres, and worked endways, completing
the arch a few feet at a time, until only a
small hole at one end of the “ length ” re-
mained. Through this lie made his exit, and
filled the cavity afterwards from below.
The stout horizontal wooden “ crown bars ”
and the “ poling boards ” behind them, which
hold up the ground, are either built in or
gradually drawn out endways as the brick-
work proceeds and they are no longer needed.
In the latter case the way must be prepared
for them by excavating an adjacent length,
the timbering of which is simplified by the
fact that the crown bars rest on the completed
brickwork at one end.
The employment of advance headings and
“ break ups ” makes it possible to excavate
and finish several lengths simultaneously;
whereas if none are used, and the tunnel is
excavated to full size at once, excavation and
masonry must proceed alternately.
The whole of the tunnel on the Glouces-
tershire side, from the Shoots to the open
cutting at the eastern extremity, was com-
pleted by August 1884 ; and by the end of
the same month the section from near the
Great Spring to the western entrance was
also finished. There remained only a short
section in the vicinity of the Great Spring,
requiring special precautions.
In order to divert the water, which could
not be confined, Sir John Hawkshaw decided
to take the spring in flank. A side heading
was therefore driven parallel
to the centre line of the tunnel Taking the
and 40 feet north of it, on a _ Great
Spring- in
much slighter gradient than Flank,
that of the tunnel itself, so as
to tap the spring at a point below the invert.
While this was being done the loose bed of the
little river Nedern, which was suspected as
being the source of the spring, received
attention in the form of a concrete invert