Engineering Wonders of the World
Volume I
Forfatter: Archibald Williams
År: 1945
Serie: Engineering Wonders of the World
Forlag: Thomas Nelson and Sons
Sted: London, Edinburgh, Dublin and New York
Sider: 456
UDK: 600 eng - gl.
Volume I with 520 Illustrations, Maps and Diagrams
Søgning i bogen
Den bedste måde at søge i bogen er ved at downloade PDF'en og søge i den.
Derved får du fremhævet ordene visuelt direkte på billedet af siden.
Digitaliseret bog
Bogens tekst er maskinlæst, så der kan være en del fejl og mangler.
306
ENGINEERING WONDERS OF THE WORLD.
Fig. 11.—THE HOODED SHIELD AND CLAY-POCKET
SYSTEM OF TUNNELLING THROUGH WATER-BEAR-
ING STRATA.
high - water, when the head was greatest,
than at times of low-water, the explanation
being that the additional weight of water so
consolidated the sand and mud through which
the tunnel was being driven as to negative
largely’the effect of the increased head. The
air losses through the face were correspond-
ingly reduced'.
CIRCUMVENTING DIFFICULTIES.
Where the ground is so loose that it will not
stand of itself, special measures are required
to prevent its falling in at the working face
and subsiding on to the tunnel lining behind
the shield when the latter is advanced, and
before the annular space left by the skin of
the shield has been filled with grout.
When water was encountered on the City
and South London Railway, Greathead adopted
what he termed his “ assisted shield system ”
of operations. He drove a
timbered heading at the roof
of the tunnel, a short distance
in advance of the shield. This
heading was roofed in with
poling boards and grout, under
cover of which the face could
The
“ Assisted
Shield ”
Method of
Tunnelling.
be excavated
A Difficulty
in
Tunnelling.
But in the case of a tunnel it is obvious that
the water pressure at the bottom is greater
than that at the top of the tunnel. As, how-
ever, the pressure of the air
must be sufficient to balance
the water pressure at the bot-
tom, there is consequently a
tendency for a large amount of air to escape
at the upper part of the face, where, if the
nature of the material is the same throughout
its depth, as it is assumed to be in this hypo-
thetical case, it would naturally take place.
In practice, of course, the nature of the
material varies greatly. In fact,
Curious un(^er the Clyde, during the
pac* construction of some tunnels
in Glasgow, it was found that
a smaller pressure was required at time of
laterally and downwards, the space so exca-
vated being supported by boards resting at
one end on the shield, and at the other
end on vertical timbers placed against the
face of th© excavation. The excavation of a
“ length ” being complete, the face timbering
had to be secured independently of the shield
before the latter could be moved forward to
permit the insertion of another ring of lining.
Two vertical timbers, called “ soldiers,” were
laid against the boards of the face, and held
tightly in position by struts projecting through
the shield and wedged against a transverse
beam jammed between the segments of the
third ring from the end. (See Fig. 10.)
A circular timber grouting-rib was now in-
serted between the heads of the hydraulic
rams and the leading face of the tunnel ring,