Engineering Wonders of the World
Volume I
Forfatter: Archibald Williams
År: 1945
Serie: Engineering Wonders of the World
Forlag: Thomas Nelson and Sons
Sted: London, Edinburgh, Dublin and New York
Sider: 456
UDK: 600 eng - gl.
Volume I with 520 Illustrations, Maps and Diagrams
Søgning i bogen
Den bedste måde at søge i bogen er ved at downloade PDF'en og søge i den.
Derved får du fremhævet ordene visuelt direkte på billedet af siden.
Digitaliseret bog
Bogens tekst er maskinlæst, så der kan være en del fejl og mangler.
364
ENGINEERING WONDERS OF THE WORLD.
Building
the
Subways.
adopted as affording a safeguard against
labour troubles. In this system there can be
no possibility of “ caving in ”
or collapse should a strike
occur and workmen be unob-
tainable. A description of the
plan followed in the building of the 6-by-7^-
foot conduits will give an idea of how the
excavations were made and the concrete sub-
way installed.
The bore in the clay was dug considerably
larger than the dimensions of the finished
subway. The mining was done by men with
hand tools, the material being removed
subsequently by mule teams. After the exca-
vators had finished their labours the cement-
ing gang appeared. Their first task was to
place in the bottom of the tunnel the required
layer of concrete, tamp it thoroughly, and
lay on top of it a lagging of boards. This
done, they placed at intervals of three feet steel
ribs of the size and shape of the inside of the
tunnel. When these ribs were in place, a
lagging of 2-inch. planks was placed between
STEEL RIBS AND LAGGING USED IN FORMING CON-
CRETE LINING OF A 12-BY-13-FOOT TUNNEL.
them, and concrete packed in behind the
lagging in layers of six inches, so as to fill up
the entire space between the wood and the
walls of the excavation. In this way subsi-
dence of the ground was avoided, because,
no matter how irregular was the mining,
every void was filled. This method was
followed to the top or key of the arch, where,
to ensure absolute accuracy, the key-blocks
were formed of lagging boards only three feet
long, the use of the short section ensuring
better work. After the ribs and lagging had
been removed, the concrete was given a facing
of cement to seal all crevices.
In the larger, or trunk, lines a somewhat
different process was followed, steel lagging
plates being used instead of planks, and 5-inch
instead of 3-inch channel irons for ribs. The
work was done in sections only three feet long,
the steel lagging plates being of just sufficient
length to span the 3-foot sections of the ribs.
The tunnelling was effected by three shifts
of men working eight hours each, the first
two shifts doing mining work and the third
How
the Work
progressed.
shift concreting. About 850
men were engaged in the three
shifts. In this way the tunnel
was mined and cementedx at
the rate of more than 300 feet per working
day, or considerably over a mile a month.
More than 300,000 cubic feet of material was
excavated in a period of three years, and
about half that quantity of stone, cement,
and gravel was put in place. As many as
thirty-eight connections had to be made
between different tunnels, and so accurately
was the surveying done that in no instance
was a junction an inch out of truth. An
air pressure of about 8 lbs. to the square
foot was maintained throughout the tunnel
during the construction period, this being
found sufficient to prevent the water from
encroaching as the work progressed.
The excavated material was removed in a
novel manner. At various points along the