Engineering Wonders of the World
Volume I
Forfatter: Archibald Williams
År: 1945
Serie: Engineering Wonders of the World
Forlag: Thomas Nelson and Sons
Sted: London, Edinburgh, Dublin and New York
Sider: 456
UDK: 600 eng - gl.
Volume I with 520 Illustrations, Maps and Diagrams
Søgning i bogen
Den bedste måde at søge i bogen er ved at downloade PDF'en og søge i den.
Derved får du fremhævet ordene visuelt direkte på billedet af siden.
Digitaliseret bog
Bogens tekst er maskinlæst, så der kan være en del fejl og mangler.
THE ROTHERHITHE TUNNEL.
two circular tunnel openings 32 feet in diameter,
which were plugged while the caisson was
being sunk, and not opened until the tunnel
was ready to pass through them.
Just above the cutting edge a steel air-tight
deck or floor was fixed, right across the caisson.
The floor was made up of steel plates and
girders, and was strong enough to withstand
the upward pressure of the compressed air
confined beneath it.
In the space below the air-tight floor the men
worked while the caisson sank, excavating the
ground over the whole area of the bottom,
and sending up the spoil through a vertical
shaft or large pipe to the air-lock ” at the
top. This air-shaft was fitted with hoisting
machinery, and a cage ran up and down it
carrying a small wagon, which on reaching the
top was run out of the cage into the air-lock,
and thence into the open air.
The process of building and sinking a caisson
was as follows :—
A level bed having been prepared on the
site of the shaft, the plates forming the cutting
edge were erected on timber supports and the
lower rings of plating gradually
Sinking added. When about 15 feet
_ .the of the caisson’s height had
Caissons. , °
been thus put together, the
framework of the air-tight floor was fitted in,
the plates being absent at this stage. All this
steelwork was then riveted together and
lowered gradually on to the ground, the sup-
ports being carefully removed and the caisson
let down by hydraulic jacks. As soon as the
cutting edge was resting on the ground, into
which it sank slightly, concrete was filled in
between the skins of the caisson to add weight.
Next, further erection of steelwork proceeded,
and at the same time excavation of the in-
terior was started, the excavated, material
being hoisted out of the caisson by derrick
cranes. Concreting then followed, and all
these operations went on simultaneously until
the work of the excavators was interfered with
55
RING OF TUNNEL LINING.
by the ingress of water. As it was not thought
desirable to use pumps to remove the water,
owing to the presence near the shafts of build-
ings which might be disturbed by pumping,
excavation was then suspended. The erec-
tion of steelwork proceeded, and the plating
of the air-tight floor was put in place and made
staunch. The air-compressing and hoisting
machinery was prepared for work, and con-
nections made for the supply of compressed
air to the caisson. As much concrete as pos-
sible was now filled in between the skins of
the caisson in order to force the cutting edge
well into the ground and so prevent the escape
of the air. Compressed air was then admitted
under the air-tight floor, a few pounds per
square inch only at first; and the water
being kept out by this means, excavation
could be continued. These operations were
repeated, and the caisson sank gradually,
being constantly built higher and weight being
added in the form of concrete. Any tendency
to get out of level was counteracted by
excavating most earth on the side which was
highest.
When everything went favourably the caisson
usually sank at the rate of about I foot per
day, work being carried on day and night.