Engineering Wonders of the World
Volume I
Forfatter: Archibald Williams
År: 1945
Serie: Engineering Wonders of the World
Forlag: Thomas Nelson and Sons
Sted: London, Edinburgh, Dublin and New York
Sider: 456
UDK: 600 eng - gl.
Volume I with 520 Illustrations, Maps and Diagrams
Søgning i bogen
Den bedste måde at søge i bogen er ved at downloade PDF'en og søge i den.
Derved får du fremhævet ordene visuelt direkte på billedet af siden.
Digitaliseret bog
Bogens tekst er maskinlæst, så der kan være en del fejl og mangler.
THE ROTHERHITHE TUNNEL.
61
consisted of a hollow cylinder, 30 feet 8 inches
in diameter and 18 feet long. The front part,
including the cutting edge, was built up of
cast-steel segments, and the
The Shield, rear part of steel plates riveted
together. The shield was stiff-
ened internally by vertical and horizontal
partitions, which divided it up into sixteen
compartments each about 6 feet square. It
was forced forward by hydraulic jacks, forty
in number, housed in the cast-steel segments
all round, close to the outside of the shield,
and whose rams pressed against the last ring
of tunnel lining erected. On the back of the
partitions were fixed two hydraulic “ erectors ”
for lifting up the lining plates and swinging
them round to any point in the ring of lining
for erection.
In order to start the shield on its journey
across the river, it was necessary to remove
the “ plug ” which temporarily blocked the
opening in the side of the
Starting shaft. This was done piece by
piece, the earth outside being
Shield. 1
supported by timbers. As
soon as the plug had been all taken out, the
shield was moved up to the face, and excava-
tion was begun. In order to move the shield,
several rings of the tunnel lining were tempo-
rarily built up behind it, resting on a timber
cradle specially prepared for them, and heavily
shored to the opposite side of the shaft.
Against the flange of the foremost of these
rings the hydraulic ranis pressed, causing
the shield to advance. The temporary rings
were removed when a few permanent rings
Advancing
the
Shield.
of the tunnel had been built in.
After tunnelling had fairly started, the
method .of working was as follows. A ring
of lining having been erected,
the miners and excavators re-
moved the earth from the front
of the shield, supporting the
with timber where required,
thrown out through the back
exposed face
The spoil was
of the shield and filled into small wagons on
the temporary rails laid in the tunnel. As
soon as sufficient ground had been removed,
excavation, was suspended and pressure ad-
mitted to the hydraulic jacks. The rams of
these, pressing against the flanges of the last
completed ring of lining, forced the shield
forward. Under favourable conditions the
shield would advance the whole distance
necessary for a ring—namely, 2 feet 6 inches
—in a few minutes, a total pressure of 2,000
to 3,000 tons being exerted. As soon as this
was done the rams were drawn in again, and
the erection of the next ring commenced.
The shield being 8 inches larger in
diameter than the tunnel lining, an annular
space of 4 inches all round the tunnel was
left void after the shield had passed. This
was filled up with grout in the
following manner. A mixture Gtouting
of ground lime and water was Lining
filled into a cylindrical steel
vessel, known as a grouting-pan, and fitted
for withstanding high internal pressure. The
grouting-pan was provided with, a horizontal
shaft, on which iron blades were fixed, and as
soon as the lime and water were introduced
the shaft was rotated so that its blades, or
paddles, should keep the mixture stirred.
When the pan was full, an air-tight cover was
fixed over the opening and compressed air of
about 80 lbs. per square inch pressure ad-
mitted to the top of the grouting-pan. At
the bottom there was an outlet, fitted with a
tap and hose-pipe. The hose ended in,.a
piece of iron pipe which was applied to the
grouting holes, of which there was one in each
plate of the lining. The tap at the bottom
of the grouting-pan was then opened, and the
air pressure forced the grout through the hose
into the 4-inch space round the tunnel. This
process was repeated until the whole space
was full of lime, which set in a short time.
The grouting was most important when tun-
nelling under the land, as by its means damage