Engineering Wonders of the World
Volume I
Forfatter: Archibald Williams
År: 1945
Serie: Engineering Wonders of the World
Forlag: Thomas Nelson and Sons
Sted: London, Edinburgh, Dublin and New York
Sider: 456
UDK: 600 eng - gl.
Volume I with 520 Illustrations, Maps and Diagrams
Søgning i bogen
Den bedste måde at søge i bogen er ved at downloade PDF'en og søge i den.
Derved får du fremhævet ordene visuelt direkte på billedet af siden.
Digitaliseret bog
Bogens tekst er maskinlæst, så der kan være en del fejl og mangler.
82
ENGINEERING WONDERS OF THE WORLD.
and it was necessary to send down a diver to
put things right. When the pumps started
again one of those in the Old Pit gave way,
and it soon became apparent that the capacity
of the pumps was not equal to overcoming
the leakage of water past the shields ; and
further attempts were accordingly postponed
until a new and very large pump should have
been added to the equipment.
Sir John Hawkshaw now decided to lower
was to remain the
new centre line of
The
Gradient
altered.
have to run
15 feet below
SIR JOHN HAWKSHAW, F.R.S.,
Engineer-in-Chief of the Severn Tunnel Works.
{Photo, Rischgitz Collection, from a painting by James
Edgdl Collins.}
brought operations to so abrupt a standstill.
Two large vertical shields of oak, having one
face shaped to the curve of
Checking the ]jnjng of yie Old pit, were
~ . constructed, lowered down
Great Spring.
the shaft, and adjusted by
divers, so as to block the openings of the
headings into the shaft. They were held
firmly up against the brickwork by stout
cross beams wedged between them (page 81).
In spite of the difficulties caused by the great
water pressure on the divers, the shields were
in position a few days after the start, and
backed with bags of Portland cement carried
through flap-doors in the woodwork.
The door between the two pits was then
closed, and pumping commenced in the Iron
Pit to lower the water sufficiently to permit
the repair of the pump that had failed. Un-
fortunately, the packing round the door leaked,
the tunnel 15 feet under the Shoots, and
alter the gradient on the Monmouthshire side
from 1 in 100 to 1 in 90. As
the gradient on the Gloucester-
shire side
same, the
that part of the tunnel would
parallel to the original line, but
it. Furthermore, in order to avoid increasing
the total length of the tunnel, it was necessary
that the depth of the Gloucestershire entrance
cutting should be also increased 15 feet, which
entailed the removal of 550,000 cubic yards of
stuff more than had been originally estimated.
A third shaft, 18 feet in diameter, was com-
menced at the Sudbrook end, close to the
Old and Iron Pits, over the line of the
tunnel. This was to be used for winding pur-
poses. At a depth of 40 feet sinking opera-
tions had to be stopped for a time, owing
to leakage from the adjacent pits ; and the
engineers had to content themselves with
making a bore hole down to the heading below
to drain the pit as soon as the works should
have been emptied of water.
Two new shafts were also begun somewhat
westwards of the point where the Great Spring
was tapped—the one for winding, the other
for pumping. The first of these
gave a great deal of trouble,
for it encountered fissured rock,
from which water spouted in
immense quantities. Profiting
by experience, the workmen
heading from the bottom of this pit into the
Interesting
Shaft-
sinking
Operations.
drove a cross