Niagara Falls 100.000-Hp. Development
Forfatter: J. Allen Johnson, G.W. Hewitt, W.J. Foster, R.B. Williamson, F.D. Newbury, Louis S. Bernstein, O.D. Dales, W.M. White, Lewis F. Moody, George R. Shepard, John L. Harper
År: 1920
Sider: 46
UDK: 621.209 H Gl. Sm.
DOI: 10.48563/dtu-0000095
Reprinted from Electrical World and Engineering News-Record
Søgning i bogen
Den bedste måde at søge i bogen er ved at downloade PDF'en og søge i den.
Derved får du fremhævet ordene visuelt direkte på billedet af siden.
Digitaliseret bog
Bogens tekst er maskinlæst, så der kan være en del fejl og mangler.
32 J
Niagara Falls 100,000 Hp. Development
FIG. 44—TUNNEL HEADING OF PENSTOCK—OUTSIDE CUT
ABOUT 20 FT. DIAMETER
section was the only one on which reinforcing bars
were used.
The seepage was taken care of by an 8-in. wrought-
iron pipe emptying into the tailrace. A T was placed at
the end of every 20-ft. section and a short length of
4-in. pipe and elbow attached to each side. Just below
each elbow a dam was built out of sacks of concrete
and just before the concrete reached the top of them
they were covered with a piece of canvas and a few
more sacks of concrete, thus leaving a permanent drain.
The bell-mouth section was concreted around wooden
forms with a bulkhead between each tunnel. Concrete
was carried to a height of 25 ft. above the bottom in
a solid mass. The first pour was about a foot above
the bottom so that the forms would not float, the second
pour to slightly above center line, and the last pour
to about 4 ft. above the highest part. The steel guides
for the gates, anchor bolts for the racks, etc., were
all set in places before concreting.
It was the original intention to concrete from the
top of the lower curve to the top of underground por-
tion with steel forms and then to connect the tunnel
concrete with the bell-mouth section with wooden forms
on the upper curve. However, as it was deemed advis-
able to rush the steelwork of the gatehouse in order to
be able to use the crane, it was decided to concrete in
the entire upper curve before doing that of the 45°
slope. This necessitated making the joining at the top
of the slope entirely underground. Pipes were placed
along the roof of the curved section so that the slope
below could be concreted at the connection.
On the 45° slope Blaw-Knox steel forms were used,
having a diameter of 15 ft. 6 in. and a length of 5 ft.
Twelve complete sections of forms and five extra invert
sections were used. Concrete in this section was con-
tinuous from bottom to top, never being less than four
batches per hour or just enough so that the top con-
crete had not set up when a new batch was poured. It
was found that by having the men walk around and stir-
ring up the top that so-called mud seams or seepage
rings were prevented from forming. Forms were only
moved during the day shift and iron workers were
employed for this work. After the first two days in
getting acquainted with their equipment and making
a few minor changes in the traveler, they averaged
four sections or 20 ft. each day. The traveler was
moved by a hoist at the top. Besides the. crew of five
iron workers on the forms, there was a concrete crew of
three men taking care of the concrete as it came
through the chutes from the top.
Lastly the steel lining was placed and concreted
around. The steel plates were assembled under the
crane in the Johnson valve chamber and when riveted
were skidded back and new sections attacked. This
steel lining extended 68 ft. in from the edge of the
cliff. The diameter was 15 ft. 6 in. except where con-
necting to the Johnson valve, at which point it was
17 ft.
With the steel penstock in place the Johnson valve
was next assembled and connected to the steel lining
and the wheel case. Riveting was then completed, burnt
rivets being cut out and replaced by new ones., In the
majority of cases, however, it was found that the elec-
tric weld on the rivet gave excellent results and made
a tight' job.
After the riveting was completed and all connections
made, the portion under-ground was concreted in, grout
pipes being placed along the roof through which grout
was afterward forced under air pressure to fill any
cavities along the roof which could not be concreted.
At the lower end of the curve, where the joints in the
concrete were made, a small keyway was left which
was painted with soft asphaltum to prevent leakage
in case of contraction. Several boxes were also placed
at the joint with f-in. pipe leading from them into the
open at the testing chamber so that any leakage froin
contraction at the joint would show.
FIG. 45—FORM FOR CONCRETING PENSTOCK TUNNEL.
CLEAR DIAMETER 15J FT.