The New York Rapid-transit Subway
Forfatter: Willialm Barclay Parsons
År: 1908
Forlag: The Institution
Sted: London
Sider: 135
UDK: 624.19
With An Abstract Of The Discussion Upon The Paper.
By Permission of the Council. Excerpt Minutes of Proceedings of The Institute of Civil Engineers. Vol. clxxiii. Session 1907-1908. Part iii
Søgning i bogen
Den bedste måde at søge i bogen er ved at downloade PDF'en og søge i den.
Derved får du fremhævet ordene visuelt direkte på billedet af siden.
Digitaliseret bog
Bogens tekst er maskinlæst, så der kan være en del fejl og mangler.
Proceedings.] PARSONS ON NEW YORK RAPID-TRANSIT SUBWAY. 21
States Government, of 20 feet, and a width of 400 feet between
retaining-walls on each side. It is crossed beneath by the East
Side line (Fig. 1, Plate 5).
As the amount of natural cover was too small to tunnel beneath,
the contractor decided, instead of making an artificial bed of the
river with clay, which would afterwards have to be removed, to
construct a roofed coffer-dam and to build the tunnel in sections
beneath this coffer-dam, taking first one half of the stream and then
the other, the Government permitting such temporary obstruction to
the channel. For this purpose a structure was designed as shown
in Fig. 10, Plate 5, consisting of two sectors of circles with a
common vertical chord, all of cast iron and surrounded by concrete.
The cast-iron lining had a shell 1 inch in thickness and ribs 6 inches
deep. As the lining was to be put in place under a roof, it was not
necessary to use a small key as ordinarily adopted in tubular linings.
The plates were, therefore, made as large as could be conveniently
handled, with a lengtli of about 6 feet longitudinally and a trans-
verse length of about 5 feet 11 inches each.
The contractor’s plan for the first half of the river consisted of
two rows of sheet-piling of 12-inch by 12-inch timbers, each timber
being grooved, and the grooves being filled with 3-incli by 4-inch
pine keys. This heavy sheet-piling was necessary to withstand the
head of about 45 feet. The rows of piling were set far enough
apart to clear the side walls of the structure. To the tops of the
sheet-piles was bolted a heavy timber roof, through which there was
an ordinary air-lock. When this structure was in place, the water
was pumped out, air-pressure was applied, and the permanent
tunnel was constructed in the caisson-chamber thus formed.
On the second half of the river the contractor decided to dispense
with tlie temporary roof by ingeniously using instead the permanent
roof of the tunnel. Rows of exterior sheet-piles were driven as
already described, with interior transverse rows of piles at 8-foot
intervals. On the interior piles were laid caps so arranged that
their tops and the top of the sheeting would be at the plane of the
centre of the tunnel when finally in place. The upper half of the
iron lining was then erected in the open and covered witli concrete,
according to the plans, but was reinforced with rods to take up any
unequal stress in the moving. To the lower part of the plates
external lugs had been cast, projecting 2 feet beyond the exterior
surface. This roof was then floated into place and sunk on top of
the sheeting and transverse caps, the exterior lugs resting on the
former. When the roof had been bolted down, the water was
pumped out and air was admitted, the excavation was completed, and