Engineering Wonders of the World
Volume III
Forfatter: Archibald Williams
År: 1945
Serie: Engineering Wonders of the World
Forlag: Thomas Nelson and Sons
Sted: London, Edinburgh, Dublin and New York
Sider: 407
UDK: 600 eng- gl
With 424 Illustrations, Maps, and Diagrams
Søgning i bogen
Den bedste måde at søge i bogen er ved at downloade PDF'en og søge i den.
Derved får du fremhævet ordene visuelt direkte på billedet af siden.
Digitaliseret bog
Bogens tekst er maskinlæst, så der kan være en del fejl og mangler.
THE COOLGARDIE AQUEDUCT.
383
To facilitate
The
Aqueduct.
level on the up-stream face, but only to
within 18 feet of the bed on the lower side ;
■and on them was raised a concrete dam, 760
feet long and 100 feet high above the river
bed, tapering in thickness from a maximum
of 120 feet to 15 feet at the crest. Nearly
70,000 cubic yards of concrete were consumed
in its construction. A draw-off valve tower
is situated on the reservoir side of the wall,
into which it is built; and a scouring valve
tower rises at a point 175 feet below the dam.
Provision is made for drawing off water at three
different levels through screens, which can be
removed for cleaning.
The Helena dam, completed in June 1902,
impounds a reservoir which., when full, con-
tains about 5,000,000,000 gallons of water.
Operations connected with the laying of
the pipe line were commenced in March 1900.
transport of materials the route
of the aqueduct followed
closely for the main part that
of the Coolgardie railway.
Where the ground was soft and not saline,
the pipes were buried; in rock and hard
ground, shallow trenches below and embank-
ments above were used ; and across salt lakes
or their dry sites the pipes ran on trestles,
an insulation of sawdust, kept in place by
galvanized corrugated iron, serving as pro-
tection against heat and cold. Where possible,
the ground was loosened by horse-ploughs to
reduce the amount of manual labour required.
One-fourth of the total material removed had
to be blasted. To promote speed, the trench-
ing was begun at several points simultaneously,
and in each section kept well ahead of pipe-
laying.
All the pipes were distributed by means
of the railway. Two cars, coupled together,
carried eight pipes, three in each of the two
bottom tiers and two on top. Eighty-eight
to one hundred and four pipes made up a
train-load. Twenty-four men, divided into
four gangs, could unload the pipes in about
an hour. When not engaged in this work
the same men busied themselves with the
trench digging, matters being so arranged
that no time should be wasted.
The pipes, laid out in their respective
positions beside the trench, were taken in
hand by successive gangs. First came the
repairers, who made good any *
defective areas of pipe coating : Pipelayers
ii-i+i i at Work,
behind them the men who
scraped off a ring of the coating for six inches
at each end of every pipe, and chipped the
ends of the locking-bars. Next in order were
the manhole-cutters ; followed by the pipe-
layers, who, with the aid of steel trestles
spanning the trench and of winding gear,
lowered the pipes into place. Then came
the ring-setters, the lead-runners, the hand
caulkers, and, last of all, the gang in charge
of the mechanical caulking-machine.
This device merits a few words to itself. A
caulking installation included a portable oil-
engine, working a dynamo, from which current
was led through a cable to a
motor on the machine. The
caulker was in two halves,
separable to permit them to
embrace the main. The motor, attached to
the top half, drove the racks operating the
steel rollers which forced the lead tightly, but
evenly, into the joints at either end of the
joint ring. Five semi-revolutions of the rollers
usually sufficed to make the joint staunch.
Knives were then substituted for the rollers
to pare off the lead flush with the rings. As
soon as the joint had been “ passed ” by an
inspector the trench was partially filled in,
completion of this work being reserved for a
gang in rear of the machine. About half a
mile of pipe could be thus caulked without
moving the generating plant to a fresh posi-
tion. Good organization and increasing skill
enabled the seven gangs to lay, joint, and
cover up nearly Ij miles of pipe per day of
eight working hours. In 1901, 90 miles of
Mechanical
Caulkings
Machine.