Engineering Wonders of the World
Volume I
Forfatter: Archibald Williams
År: 1945
Serie: Engineering Wonders of the World
Forlag: Thomas Nelson and Sons
Sted: London, Edinburgh, Dublin and New York
Sider: 456
UDK: 600 eng - gl.
Volume I with 520 Illustrations, Maps and Diagrams
Søgning i bogen
Den bedste måde at søge i bogen er ved at downloade PDF'en og søge i den.
Derved får du fremhævet ordene visuelt direkte på billedet af siden.
Digitaliseret bog
Bogens tekst er maskinlæst, så der kan være en del fejl og mangler.
THE GREAT VICTORIA BRIDGE. 207
To with-
stand the
enormous
pressure of
the ice, the
bridge piers
had to be
ELEVATION OF PIER. mos^
solid con-
struction. It was decided to build them
up from the solid rock with stones weigh-
ing from 5 to 20 tons apiece. The down-
stream face of a pier was vertical ; the up-
stream face carried a large sloping ice-breaker,
sharp edged, of stones bonded with iron
clamps. This gave the pier an outline roughly
resembling that of a boot, up which the ice
would climb until its own weight shattered it
on the sharp angle of the breaker. At summer
water-level twenty-two of the piers measured
90 feet by 18 feet; the other two, those for
the central span, 90 feet by 28 feet.
The employment of divers in an 8-mile
current being impracticable, some plan had to
excluding the water from the
sites of the piers and abutments,
and working on a dry bed. In
a sluggish stream the forma-
tion of cofferdams would have
presented little difficulty ; here
the reverse was the case. After careful de-
liberation, the engineers decided to build in
the quieter water near the banks the cais-
sons needed to form the walls of a dam, tow
them into position, sink them, and line them
with an inner wall of puddled clay, rammed
hard down in a puddle chamber so as to
exclude all water when the pumps should be
set to empty the dam. To prevent the cais-
sons shifting when once sunk, they were pro-
vided along the outside with steel piles, moving
in grooves, which could be driven down into
the bed of the river and so anchor the caisson.
During the winter of 1854, as soon as the
ice-bridge had formed, the contractors began
be devised for
Plan of
Pier-
building
Operations.
Marking
out the
Pier Sites.
each pier was
operations by marking out the positions of
the piers on the ice, cutting holes, and taking
soundings, while a road of
a more or less level character
was made, in the line of a
bridge, over the rudely packed
ice. The site for the centre of
carefully marked by sinking an iron bar, 5
feet long and 4 inches in diameter, into the
bed of the river, to serve as a guide for opera-
tions in the spring following. This done, large
cribs of woodwork and stone were sunk in
position above the piers to act as anchorages
while the dams were being floated into position.
PLAN OF PIER AND REMOVABLE COFFERDAM INSIDE
WHICH IT WAS CONSTRUCTED.
The pointed end faces up-stream.
The spring of 1854 opened early. On the
24th of May the first caisson to form part of
the dam for the north abutment was towed
up-stream and sunk, and in
due course that part of the Work
, j . . . commences,
river-bed on which the masonry
was to rise had been pumped dry. The first
stone was laid at the end of August 1854, and
before work ceased for the winter more than
85,000 cubic feet of stone had been set. Mean-
while the approach embankment was built of
stone faced with masonry on the up-stream
side, and the dam for No. 1 pier—namely, that
nearest the north abutment—was got into
position and sunk. This pier was finished in
November. Great trouble was experienced
during the making of the dam for No. 2 pier,
consequently for some of the other piers large
cribs were used instead of caissons as barriers
against the water.