Engineering Wonders of the World
Volume I
Forfatter: Archibald Williams
År: 1945
Serie: Engineering Wonders of the World
Forlag: Thomas Nelson and Sons
Sted: London, Edinburgh, Dublin and New York
Sider: 456
UDK: 600 eng - gl.
Volume I with 520 Illustrations, Maps and Diagrams
Søgning i bogen
Den bedste måde at søge i bogen er ved at downloade PDF'en og søge i den.
Derved får du fremhævet ordene visuelt direkte på billedet af siden.
Digitaliseret bog
Bogens tekst er maskinlæst, så der kan være en del fejl og mangler.
328
ENGINEERING WONDERS OF THE WORLD.
SECTIONAL VIEW OF CAISSON.
Showing working chamber at the bottom,
{Photo, J. Valentine and Sons ')
with men using hydraulic spades,
shafts for men and materials, air-locks, platforms, etc.
the caisson. The operation took nearly ten
months, but it proved a great success. The
caisson floated once more, and reached its
final position nearly a year after its three
fellows—namely, in February 1886.
When excavation under the
Filling- __ caisson had been completed,
the Air- air-chamber was cleared
chambers. materials used during
the sinking. The smiths then
provided the bottom of the material shafts
with flap doors opening downwards, and re-
placed the large locks at the
top by smaller ones. At a
given signal the men below
closed the flap of a shaft.
Those above opened the cock
and filled the tube up with
freshly mixed concrete. Then
the cock was closed and the
first party admitted air into
the shaft above the concrete,
and, when the pressure there
was the same as that in the
chamber, released the flap,
allowing the contents of the
shaft to pour out. The con-
crete was then rammed hard
into every hole and cranny,
from floor to roof, work
proceeding from the circum-
ference towards the shafts,
which, after the men had
finally withdrawn, were filled
with cement grout.
The next operation was to
fill the caisson space above
the air-chamber with con-
crete up to
low - water
level. Whßn
the material
The
Granite
Piers.
had set, granite courses were
built on it to a height of
18 feet above high-water
level. Three stout iron rings, incorporated
into the work, reinforced the granite, in
which were enclosed forty-eight steel bolts,
25 feet long and 2J inches in diameter,
having a 2-foot square anchor-plate at the
bottom, and a long screw thread cut on
the top, where the diameter increased to
three inches. The greatest care was needed
to keep this large array of bolts in the exact
positions corresponding to the holes in the
massive bed-plates which crowned the pier.
A bed-plate was 37 feet long and 17 feet