ForsideBøgerA Treatise On The Princip… Of Harbour Engineering

A Treatise On The Principles And Practice Of Harbour Engineering

Forfatter: Brysson Cunningham

År: 1908

Forlag: Charles Griffin & Company

Sted: London

Sider: 410

UDK: Vandbygningssamlingen 134.16

With18 Plates And 220 Illustrations In The Text

Søgning i bogen

Den bedste måde at søge i bogen er ved at downloade PDF'en og søge i den.

Derved får du fremhævet ordene visuelt direkte på billedet af siden.

Download PDF

Digitaliseret bog

Bogens tekst er maskinlæst, så der kan være en del fejl og mangler.

Side af 416 Forrige Næste
174 HARBOUR ENGINEERING. and harbour walls, and the space between was occupied by two lines of railway for conveying men and materials ; and in this way the whole width of the top of the stage, viz., 70 feet, was occupied. “ About the middle of May in every year the first block was lowered by the helmet divers’ gantry to its place. The helmet divers’ stage was suspended by iron rods from the beams of the main stage, and hung about 10 feet below it. To this stage wrought iron ladders were attached for the convenience of divers descending to their work. Six divers were under water together—four on the seaside and two on the harbour side. They remained down four hours at a time, when there was a shift; and there were three shifts in the day. The life-line men and pumpers remained on the work all day, but the pumpers were relieved every half-hour. The divers’ apparatus and the stage were removed every night, so treacherous was the sea, for even in summer it was not safe to leave anything at the level of the divers’ stage; but at the height of the main stage, 10 feet higher, or 20 feet above high water, the sea seldom disturbed anything. The mode of bringing the work up was by taking advantage of the spring tides ; thus it was expected of the divers that, in a fortnight, they would bring the diving work up to the level of low water, for a distance seaward of 60 feet, ready for the masons. Whatever excavation was required for the lowest course, it being a great deal more at some times than others, or however rough the sea had been, the divers never failed to prepare a length of 60 feet ; but they frequently went down a second time for an extra shift to accomplish this. The average day’s work of a diver in the year 1860 was 8J cubic yards of building; in 1861 it was 11 cubic yards; and in 1862 it was 14 cubic yards. Their work was excavating foundations, receiving the granite face-stones for the sea-wall, and setting the granite and concrete blocks of the sea and harbour walls. The stones and blocks were speedily lowered by a single chain 45 feet from the top of the stage by the gantry crabs and a rope-break. This latter was a piece of rope, with rope yarn twisted round, made fast to the frame of the crab and then fastened to the pinion shaft of the single and double gear. The chains employed were of the best charcoal iron ^ inch thick, and they were only used for two seasons. “ The divers’ work being ready for the masons, to the level of low water of spring tides, two days before full or new moon, the resident engineer gave orders to commence setting the face-stones in cement, if, in his opinion, the tide fell low enough ; otherwise he could stop the works. The masonry of the breakwater on the sea face was of granite and native Alderney stone • on the harbour side it was of native stone, and the space between was filled in with backers and small rubble. The backers were as large as the machinery would lift, and were set in Medina cement and sand, in the proportion of 1 part of cement to 2 parts of sand. Sand suitable for building occurred in abundance in the island. No better cement could have been had for the purpose, for very often the masonry, ten minutes after it was built, was covered with water. No large stock of cement was laid in, as its quick setting qualifies were impaired by time. The masons endeavoured to keep the work done at each