ForsideBøgerA Treatise On The Princip… Of Harbour Engineering

A Treatise On The Principles And Practice Of Harbour Engineering

Forfatter: Brysson Cunningham

År: 1908

Forlag: Charles Griffin & Company

Sted: London

Sider: 410

UDK: Vandbygningssamlingen 134.16

With18 Plates And 220 Illustrations In The Text

Søgning i bogen

Den bedste måde at søge i bogen er ved at downloade PDF'en og søge i den.

Derved får du fremhævet ordene visuelt direkte på billedet af siden.

Download PDF

Digitaliseret bog

Bogens tekst er maskinlæst, så der kan være en del fejl og mangler.

Side af 416 Forrige Næste
PIERHEADS, QUAYS, AND LANDING-STAGES. '95 140,000 cubic feet of stone, bulking from 14 to 35 cubic feet a-piece, were deposited and formed into a berme 10 feet in width, with a slope of 2 to 1. In order to secure this stone-work in position, large blocks, containing 175 cubic feet each, were placed on top. The blocks were made of granite fragments and cement mortar in the proportion of 1 to 3 ; they had a length of 6 feet 6 inches, a width of 5 feet, and a height of 5 feet 6 inches, and they weighed 12J tons. Work proceeded on these lines from 1892 to 1894. A storm in November 1894, however, once more wrecked the pierhead, destroying the uncompleted berme and its covering. All burrs and blocks lying in less than i feet 6 inches of water were dislodged, and some of them swept up the slope. Subsequent measures for the protection of the pierhead have been directed to the consolidation and maintenance of the mound, but on somewhat different lines, experience having indicated that the largest blocks formed the best covering material. Thus, in addition to a large number of the smaller blocks which served to fill up gaps and to provide a flat surface, in 1895 eleven blocks of 635 cubic feet, and in 1896 ten blocks of from 530 to 1(65 cubic feet, were bedded on the rubble work in concrete composed of granite and cement mortar. Yet these measures were attended by no better success than that of their predecessors. The very largest blocks, weighing 120 tons, were sooner or later dislodged by storms and driven down the slope. They were continually restored, until finally, in November 1899, a gale wrought such serious havoc that even the lower portion of the pierhead foundation was exposed and partially withdrawn. As a consequence, the whole weight of the super structure came to rest upon the piling and staging which had been erected for pile-driving machines and rail-tracks during the construction of the mole and which had been left buried in the mound. The only plan now was to fill up the cavities, and this was done by means of stones and sacks of concrete packed within a circumscribing ring of blocks of 350 cubic feet, each set in a double row. But, before this work could be completed, fresh disasters occurred. The blocks were disturbed, and some of the rubble carried away, in November 1900. No satisfactory repairs could be effected during the winter season, and in the following April a violent westerly gale once more devastated the whole pierhead. The staging-piles broke; the crack which had formed at the junction of the mole and pierhead at the time of the initial destruction of the terrace, widened out on the Xonr side? a wid? °f 4 feet 3 inches’and the Pærhead’ a ^ge mass of 20,660 cubic feet, aud having a weight of 1680 tons, was slewed on its axis through 12 feet towards the sea, and left with its outer edge depressed to the extent of 4 feet 4 inches. In this condition it rested upon a few projecting peaks or the mound. 1 J 6 During these experiences, it was observed that a concrete block of 1553 cubic feet, which had been set on the deop-water side of the head, had not