The Works Of Messrs. Schneider And Co.
Forfatter: James Dredge
År: 1900
Forlag: Printed at the Bedford Press
Sted: London
Sider: 747
UDK: St.f. 061.5(44)Sch
Partly Reproduced From "Engineering"
Søgning i bogen
Den bedste måde at søge i bogen er ved at downloade PDF'en og søge i den.
Derved får du fremhævet ordene visuelt direkte på billedet af siden.
Digitaliseret bog
Bogens tekst er maskinlæst, så der kan være en del fejl og mangler.
THE ALEXANDER III. BRIDGE.
143
the bridge has to bear these strains only at short intervals,
when it is shifted from one series of arches to the following.
For this operation a calm day is always chosen, so as to
reduce the strain on the horizontal stay girder, the moment
of flexure of which, under the action of the wind, is also at
a maximum for the 120-metre (394-ft.) spån.
It will be seen, therefore, that the roller bridge behaves
differently during shifting and during érection. In the
first case, it rests solely on the end tresties, mounted on
wheels, and is calculated to be self-supporting, while bear-
ing the surcharge due to the suspended flooring and
érection tackle. In the second case, it is lifted by screw
jacks and lowered on supports in a line with the Inter-
mediate piles, so that it can be compared to a three-span
bridge, i.e., with one 53-metre (174 ft.) central spån and
two 33.50-metre (110-ft.) shore spåns. The supports on
the piles are, however, maintained slightly lower than
those on the abutments, as the weight of the arches that
acts on the middle part would cause the bridge to sag in
the centre, which would tend to make it rise with regard
to the roller tresties. This, however, might have been
avoided by curving the girders ; but, on the other hånd, it
would have been more difficult to deal with girders so
shaped, and it was deemed préférable to let the roller
bridge be slightly curved in its central part during érection,
which, moreover, facilitâtes placing the vous,soirs.
Erecting the Roller Bridge.—It was thought, at first,
that the bridge could be erected on one of the banks and
floated in place ; owing, however, to its great dimensions,
especially its height, 17 metres (55 ft. 9 in.) above the
rivei- level, the idea was abandoned. In erecting, great
difficulties had to be overcome, as there was not sufficient
space available on either bank to erect it completely, nor
indeed, enough to erect a section that would cross the
53-metre (174 ft.) wide channel. The bridge was there-
fore built in three operations.
In order to reduce the strains developed in the bridge
framework during overhang in the second operation, one
end was fitted with a light tapering head 15 metres (49 ft.)
in length (Plate LXXXVIL).
During érection the lower frames had to transmit to
the lattice bars the reactions from the Hearings, when they
were not immediately above the bearings. These bars
had, therefore, in each panel consecutively, as it came
above the bearings, to bear local strains which inereased
the work upon them to a large degree. The framea had
been stiffened to resist local strains, the height of the
webs having inereased from .450 metre (17üin.) to .550
metre (21f in.) ; in addition, steel stanchions join the
central part of these frames to the lattice work, in a line
with the middle of each panel. As these arrangements
were not thought sufficient, strengthening was completed
by the addition of an angle-bar to the top of the frame
webs in the panels that were liable to be most distressed.
As the river traffic was on no account to be interfered
with, a floating row of piles was moored, for the sake of
prudence, in the centre of the channel, and was adjusted
at such a level that by means of a few wedges it was
possible to place it in contact with the underside of the
bridge. This was done only as a precautionary measure,
and the device was not used at all during the érection
of the bridge, the 53-metre (174 ft.) wide channel being
crossed without any difficulty. The strain on the metal
reached 15 to 16 kilogrammes per square millimétré
(9.52 to 10.16 tons per square inch) of section at the
end of the operation.
Three causes contributed to the lowering of the end of
the girder during érection and launching: 1. Deflection of
the beam under the action of the dead load ; 2. variations
in the direction of the bearing line, owing to the settling of
the scaffolding, elastic shortening of the woodwork, &c.;
and 3. local deformation produced in the lower framing.
The first element was estimated at .15 metre (5J in.), and
to compensate for the elements that could not be calculated
in advance, the end was raised by .20 metre (7-g- in.). All
the operations were carried out without mueh trouble ;
each one took a half day, and during the second operation,
navigation was stopped from 5 A.M. to 7 A.M. only.
The forward travel of the bridge was obtained by
means of two winches working on two sets of tackle fixed
to the set of piles to the right. The shifting device com-
prised beams fitted with two or four rollers, according to
the loads to be transferred to the scaffolding.
The roller bridge behaved well, as also did the wood
scaffolding. During the greatest overhang the support
placed above the starting point settled by 16 millimétrés
(f in.) ; while that in the rear settled by 5 millimétrés
(t3k in.), the end of the bridge having drooped 136 milli-
métrés (5f in.). The end, however, met its bearings with-
out trouble and without it being necessary to lift it, the
complété launching taking place without any stoppage.
To add to the précautions already taken, the panel uprights
subjected to the greatest strains were strengthened with
timber stanchions placed in the centres.
Erecting the Arches.—Each arch is erected by start-
ing from both ends at once ; therefore two ribs in course
of being laid occupy four gangs who meet at the key. The
varions operations are shown in the illustrations, Figs.
405 to 437, Plates LXXXVIL to XCI. Two steam
crânes take the sections from the dépôt on the banks,
and lift them on trucks which are used to carry them
under the service bridge, from which they are taken by
means of steam winches. These are double-acting by
means of cables, and serve both for raising the voussoirs
and conveying them to the spot where they are to be fixed ;
the roller bridge is fitted with tracks for this purpose, on
which run the érection trucks, two in number, for each rib.
Each truck has, therefore, to serve a 60-metre (196 ft.
10 in.) run of ribs ; this nécessitâtes a perfect system of
conductors both for the endless conveying chain and for
the lifting cable ; to this effeet the endless chain runs in a
trough made of sheet steel while the cable is supported on
specially-shapecl sheaves, arrangée! so as to allow free
travel for the trucks. These sheaves are in two parts,