Niagara Falls 100.000-Hp. Development
Forfatter: J. Allen Johnson, G.W. Hewitt, W.J. Foster, R.B. Williamson, F.D. Newbury, Louis S. Bernstein, O.D. Dales, W.M. White, Lewis F. Moody, George R. Shepard, John L. Harper
År: 1920
Sider: 46
UDK: 621.209 H Gl. Sm.
DOI: 10.48563/dtu-0000095
Reprinted from Electrical World and Engineering News-Record
Søgning i bogen
Den bedste måde at søge i bogen er ved at downloade PDF'en og søge i den.
Derved får du fremhævet ordene visuelt direkte på billedet af siden.
Digitaliseret bog
Bogens tekst er maskinlæst, så der kan være en del fejl og mangler.
26 ]
Niagara Falls 100,000 Hp. Development
Enlarging Channels and Erecting
the Station
Special Drill Boat Used for Excavating Channel
Due to High Current Velocities.
Details of Cofferdam Construction.
By O. D. Dales
Construction engineer Niagara Falls Power Company,
Niagara Falls, N. Y.
THE excavation of the 20-ft. channel from the head
of the canal out into the Niagara River was through
limestone for the first 1,000 ft. out from the shore, the
balance being in hardpan. The drilling was done by
four drill boats with steam drills, the holes being placed
on 4-ft. centers each way. Drilling was carried down
to 3 ft. below the finished grade. The dredging was
done by three dipper dredges with 64-yd. buckets. The
excavated material was placed in dump scows and towed
out into the river just above the upper rapids, this class
of excavation being similar to most dredging opera-
tions in large rivers. Disposing of the excavated mate-
rial was rather difficult on account of the location of
the dumping ground. Extreme caution was exercised
by the contractor, but in spite of this one dump scow
broke its two tow lines and floated down the Canadian
channel to below the upper cascade rapids where it
went aground on some rocks about 800 ft. from the
Canadian shore. The two men on board were removed
by the Fort Niagara life-saving crew by means of
shooting a line out to the scow and bringing them
ashore in the breeches buoy.
Most of the piers for supporting the two inner lines
of booms were built in previous years and consist of
concrete piers upon rock-filled timber cribs. These
offered considerable resistance to the water so another
type of pier has been developed which consists of
Lackawanna steel sheet piling driven through the hard-
pan to the rock, which is from 6 to 15 ft. below the
bottom of the river. These piers were built as 6 ft.
diameter cylinders filled with concrete from the hardpan
to the top. Details are shown on an accompanying
drawing. This type of pier was used in the outer line
of booms and were placed 50 ft. apart except in the
deep dredged channel where they were 150 ft. apart.
As there was no hardpan in the dredged channel the
bottom of the 6-ft. cylinders were encased in 19-ft.
6-in. square concrete bases 12 ft. high. The past winter
was very severe and a large amount of ice passed
through the Niagara River thoroughly testing these
piers and booms.
It has been the intention for a number of years to
deepen the canal to 20 ft. below mean water level with
a cross-section approaching as nearly as possible the
typical section shown on the drawing herewith. Exca-
vation had been carried on in the canal for a great
number of years and up to 1912 had been excavated
on the right-hand half, looking downstream, down to
20 ft. for nearly the entire length of the canal. The
left-hand side of the canal was left at 14 ft. deep,
while under the bridges it was approximately 14 ft.
deep on both sides.
In order to have sufficient water available for the
operation of the new plant along with the old plants
it was necessary to excavate and clean up the canal
to a depth of 20 ft. for the entire width approaching
the typical section shown on the drawing. The excava-
Stoindard 5O-€t. Boom
FIG. 35—ICE PROTECTION AT CANAL INTAKE ON NIAGARA RIVER