Niagara Falls 100.000-Hp. Development
Forfatter: J. Allen Johnson, G.W. Hewitt, W.J. Foster, R.B. Williamson, F.D. Newbury, Louis S. Bernstein, O.D. Dales, W.M. White, Lewis F. Moody, George R. Shepard, John L. Harper
År: 1920
Sider: 46
UDK: 621.209 H Gl. Sm.
DOI: 10.48563/dtu-0000095
Reprinted from Electrical World and Engineering News-Record
Søgning i bogen
Den bedste måde at søge i bogen er ved at downloade PDF'en og søge i den.
Derved får du fremhævet ordene visuelt direkte på billedet af siden.
Digitaliseret bog
Bogens tekst er maskinlæst, så der kan være en del fejl og mangler.
28]
Niagara Falls 100,000 Hp. Development
t-yd. steam shovel. The rock was drilled and blasted
in the dry down to about 2 ft. below the water surface
by leaving a narrow ridge of solid rock as a cofferdam.
The blasted rock was removed into dump wagons by the
t-yd. steam shovel.
The next 11 to 13 ft. down was drilled and blasted in
the dry and removed with a dipper dredge. The drill-
ing was done with tripod drills, holes being placed about
4 ft. apart each way and along the side it was close
drilled. These holes were 6 to 8 in. apart. It has been
found that this close drilling in this class of rock gives
a comparatively smooth wall for the side of the cut.
In the excavation above water 0.8 lb. of 60 per cent
dynamite per yard was used.
The lower 9 ft. of excavation for the basin enlarge-
ment was drilled and blasted from the drill boat and
removed by the dipper dredge along with the deepening
of the rest of the basin and in
the same manner as the canal
excavation.
Much of this basin enlarge-
ment was done in the summer
and fall of 1918 when it was
imperative on account of the
war to keep all the old power
plants running- to their utmost
capacity. The blasting up of
the bottom of the basin, the
ridge formed in front of the
dipper dredge and the dredge
with scow restricted the cross-
sectional area so as to increase
the velocity of the water very
much. These conditions are
shown in the view on p. 29,
which was taken Oct. 19, 1918.
The work was done in strips
the length of the basin and
sufficiently wide for the con-
venient operation of the
dredge. Each strip was com-
pleted through before begin-
ning another so as to reduce the cross-section as little
as possible.
The forebay was built in rather cramped quarters,
being separated from the basin by the basin road and
between two large flour mills on the north and south,
while on the west were busy switchtracks.
The old west wall of the canal basin, which is shown
on p. 29, is built of concrete upon limestone. The
top of the rock is at about water level. Under the
roadway the inlets to the forebay have been built.
In the construction of the forebay this west wall with
a wider strip of rock under it was at first used as a
natural cofferdam for the excavation. As soon as the
basin had been widened and deepened enough by dredg-
ing to allow a cofferdam to be built in it and also
permit about 7000 sec.-ft. of water to pass to old
Station No. 3, a cofferdam was built. It was quite
important that this cofferdam should restrict the flow
as little as possible. With this in mind a narrow coffer-
dam was built of Lackawanna 12| x f-in. straight web
steel sheet piling in water varying in depth from 16
to 24 ft. The cofferdam consisted of 18 oval-shaped
pockets. The size of the typical pocket in plan is 14 ft.
4 in. long, 9 ft. 10 in. wide at the mid-section, and
I ^-TELESCOPIC PIPE Fasteninq
I j 4''Diam. 6'long
6 ft. 5 in. at the end where it joins the adjacent pocket.
The outside row is composed of piles 24 ft. long and
the inside row of 20-ft. piles.
In the construction, timber trusses were first built
in lengths 28 ft. long and 8 ft. deep, using 12 x 12-in.
timbers for the chord members and 8 x 8’s for the
diagonal members. These were built on the bank along
side of the basin, launched, and floated into their
place which was along the old concrete basin wall.
Upon the cofferdam side of the truss were fastened
timbers shaped to fit the outside of the pockets. After
the truss was in place templets made of two thick-
nesses of 2-in. plank and the shape of the inside of
the pocket were floated into place and the sheet piling
placed around these templets and against the truss.
Work was begun at the upstream end so as to take
advantage of the current. As soon as the piling for
5'long
FIG. 38—DRILL BOAT USED IN CANAL EXCAVATION
one pocket was placed they were driven with a light
piledriver so as to drive them through any loose rock
which might be on the bottom of the basin and cause
them to fit as closely as possible to the solid rock.
After this a diver went down into the pocket and
closed up any openings that were found between the
piling and the rock, using bags filled with concrete.
Good rich concrete was then poured in the bottom of
the pocket for a depth of about 2 to 3 ft. so as to
properly seal the bottom and thoroughly fasten the
cofferdam to the rock. The pocket was then filled
up to the top with ordinary gravel, the pressure of
this gravel causing the pockets to bulge slightly and
completely tightening the joints. This made a very-
narrow cofferdam but it was thoroughly fastened to
the rock at the bottom by concrete and at the top
supported by two stiff wooden trusses.
In excavating the rock back of this old basin wall
as much solid rock was left as possible between the
piers to act as pilasters for supporting the old concrete
wall which was receiving the load thrust upon it
through the trusses from the top of the cofferdam.
As soon as the piers were completed the old concrete
wall was removed directly in front of the piers so that