Niagara Falls 100.000-Hp. Development
Forfatter: J. Allen Johnson, G.W. Hewitt, W.J. Foster, R.B. Williamson, F.D. Newbury, Louis S. Bernstein, O.D. Dales, W.M. White, Lewis F. Moody, George R. Shepard, John L. Harper
År: 1920
Sider: 46
UDK: 621.209 H Gl. Sm.
DOI: 10.48563/dtu-0000095
Reprinted from Electrical World and Engineering News-Record
Søgning i bogen
Den bedste måde at søge i bogen er ved at downloade PDF'en og søge i den.
Derved får du fremhævet ordene visuelt direkte på billedet af siden.
Digitaliseret bog
Bogens tekst er maskinlæst, så der kan være en del fejl og mangler.
Niagara Falls 100,000 Hp. Development
[29
timber struts could be placed
between the trusses and the
piers, thereby transferring
the pressure of the top of the
cofferdam from the old wall to
the new piers. The old wall
and the rock between the piers
was then blasted and removed.
Excavation back of the cof-
ferdam was carried down to a
depth of about 6 to 8 ft. be-
low the bottom of the coffer-
dam and within an average of
about 2 ft. of the inside line of
the cofferdam, and in a few
places the rock broke back
of this inside line. The con-
crete seal which had been
placed in the bottom of the
pockets could then be seen
quite plainly in such places
and showed that a good bond
with the rock bottom had been ’ FIG 39_________dredging
made. As the excavation pro-
gressed downward and closer to the cofferdam, extra
struts of 12 x 12-in. timbers were placed from the piers
to the cofferdam. The view on page 31, which was taken
back of the cofferdam, shows the piling of the cofferdam
on the right, the piers on the left with the timber
trusses above, and the excavation carried up to within
about 2 ft. of the cofferdam. At the time when the ex-
cavation of the forebay was completed the entire leak-
age of the cofferdam and rock did not exceed 4 sec.-ft.
On page 30 is shown the completed cofferdam. As
some of the piling drove into the bottom farther than
was anticipated on account of there being more loose
rock on the bottom than was expected, it was necessary
to build a light wooden cofferdam along the top in order
to take care of any extreme high water.
It was necessary to locate the power house as close
to the cliff as possible in order to get the foundations
and tailraces on solid rock. The top of the cliff here
is about 218 ft. above the water level in the gorge.
Extending upward about 100 ft. from the water surface
is a talus slope which consists of a layer of about ten
feet of loose rocks which had fallen from the cliff.
Excavation was begun at the toe of the slope using
a t-yd. steam shovel, the loose rock being washed down
to the shovel with a hydraulic giant. This hydraulic
giant had a 4-in. nozzle and the water was supplied
to it by a 10-in. pipe line carried from three of the
9-ft. penstocks in old Station No. 3. This gave a work-
ing head of about 180 ft. at the nozzle. As soon as
sufficient area had been cleaned off with the hydraulic
giant, drilling and blasting of the solid rock was begun.
Excavation of the solid rock was carried down to about
4 ft. above mean water level. Then a concrete coffer-
dam was built on solid rock the length of the proposed
power house and about 60 ft. west of the west wall
of power house. Excavation was then carried down
to 23 ft. below mean water level. The excavation
above EL 370 consisted of shale and limestone, from
this to the water surface alternate layers of Medina
sandstone and red shale, and below the water level
was solid Medina sandstone.
As soon as the excavation was completed the con-
IN A STIFF CURRENT IN THE NIAGARA HYDRAULIC CANAL
crete foundations for the turbines were poured. The
mixing plant was located at the top of the cliff. The
gravel was brought in on cars and unloaded onto a
belt conveyor which carried the gravel to a storage
pile. It was then conveyed from the storage pile to
hoppers over the mixers by a clamshell bucket operated
from a derrick. The mixed concrete was conveyed
through flexible sheet iron, elephant trunk, chutes sus-
pended in cables extending from the top of the cliff
to the bottom.
The piers and heavy reinforced-concrete floors for
supporting the entire units were completed up to the
bottom of the wheel cases. Then the wheel cases were
set. After the cases were set the concrete piers and
power-house floor were poured.
FIG. 40—LOW BOOM DREDGE FOR WORK UNDER BRIDGES