Niagara Falls 100.000-Hp. Development
Forfatter: J. Allen Johnson, G.W. Hewitt, W.J. Foster, R.B. Williamson, F.D. Newbury, Louis S. Bernstein, O.D. Dales, W.M. White, Lewis F. Moody, George R. Shepard, John L. Harper
År: 1920
Sider: 46
UDK: 621.209 H Gl. Sm.
DOI: 10.48563/dtu-0000095
Reprinted from Electrical World and Engineering News-Record
Søgning i bogen
Den bedste måde at søge i bogen er ved at downloade PDF'en og søge i den.
Derved får du fremhævet ordene visuelt direkte på billedet af siden.
Digitaliseret bog
Bogens tekst er maskinlæst, så der kan være en del fejl og mangler.
30 ]
Niagara Falls 100,000 Hp. Development
Manufacturers of all machinery were requested to
ship in pieces not heavier than 50 tons, also that each
piece must pass through a door 12 ft. wide and 16 ft.
high.
The equipment for the power house was carried
below the bank by means of a large 50-ton crane which
is a permanent structure built in 1906 and was used
in the construction of old Station No. 3. This 50-ton
crane is operated over a crane runway, the westerly
end of which is a cantilever extending 53 ft. over
the edge of the cliff and running back easterly over
the switchtracks which are about 200 ft. from the
edge of the cliff. The crane has a 50-ton and a 5-ton
hook with a total lift of 235 ft. By means of this
crane all equipment was lifted from the railroad cars
upon the switchtracks, carried out to the end of the
cantilever and lowered 225 ft. below unto a car which
runs on a standard-gage track into the south end of old
Station No. 3 and there turns into the new station.
Within the new station are two electric cranes of 100
tons each. By means of these cranes all parts of the
equipment were easily carried from the car and dis-
tributed to their proper place in the power house. In
the erection of the turbines and generators it was
necessary as the parts were assembled to make lifts
from 150 to 200 tons. This was accomplished by using
the two cranes together by means of a large whiffle
tree, which was a 200-ton capacity box girder beam
arranged so that the two cranes should be readily-
hitched at each end with a large lifting hook in the
middle of this beam.
Tunneling and Lining the Penstocks
Method of Driving Tunnels Up Through 350 Ft. of Rocks
and Placing Penstocks Steel and
Johnson Valve
By G. W. Hewitt
Field engineer Niagara Falls Power Company,
Niagara Falls, N. Y.
THE three penstocks of Station No. 3 extension are
identical, and except for a few minor details dur-
ing the construction, the conditions met were the same.
Each tunnel was driven from the lower portal up
through the rock to the top, a distance of 350 ft.
Excavation started at the face of the deep excavation
of the power house and ended at the face of the excava-
tion of the forebay. The excavation of the bell-mouth
section inside the limits of the forebay gatehouses was
open excavation and was part of the excavation of the
forebay.
The center line of tunnel was level at El. 353 to the
P. C. of the lower curve, the P. I. of which was 86
ft. from the portal. At this point the line turned 18°
19' to the right and 45° to the vertical, making the
actual intersection angle 47° 50'. The two tangents
were connected by a 40-ft. radius curve. The inclined
section of tunnel was 45° to the vertical until the upper
curve was reached, which also had a 40-ft. radius, and
then into the open excavation of the bell-mouth section,
the center line of which was El. 538, or a vertical dis-
tance of 185 ft. from center of lower horizontal section
to horizontal section of bell-mouth.
The diameter of finished tunnel is 15 ft. 6 in. and
the plans called for a minimum of 18 in. of concrete,
making the excavation 18 ft. 6 in. in diameter theo-
retically, although sunflower cross-sections showed that
the diameter of excavation averaged 20 ft.
Excavation was started at the lower portal, using
four water Leyner column drills,, and the entire head-
ing, or upper half of the tunnel, drilled and shot.
Disposal was made on the horizontal section by shovel-
©A = l'x9'Drift
D -Ribs and 50% of Dench
C -Remainder of Bench
FIG. 42—STAGES IN PENSTOCK TUNNELING OPERATION'S
ing the rock into 4-yd. cars, which were hauled out by
steam dinkeys. After the bench had been uncovered,
it was then drilled and shot and the material disposed
and the track run back. At the end of the horizontal
section a heavy timber hopper was built under which
the cars could be run and loaded so that after shoot-
ing the rock would roll down the 45° slope onto the
hopper. Above this point and for the remainder of the
tunnel, the drilling and shooting were done in three
operations, as can be seen from the sketch shown above.
FIG. 41—COFFERDAM AT FOREBAY OF EXTENSION TO STATION NO. 3, NIAGARA FALLS POWER COMPANY