Niagara Falls 100.000-Hp. Development
Forfatter: J. Allen Johnson, G.W. Hewitt, W.J. Foster, R.B. Williamson, F.D. Newbury, Louis S. Bernstein, O.D. Dales, W.M. White, Lewis F. Moody, George R. Shepard, John L. Harper
År: 1920
Sider: 46
UDK: 621.209 H Gl. Sm.
DOI: 10.48563/dtu-0000095
Reprinted from Electrical World and Engineering News-Record
Søgning i bogen
Den bedste måde at søge i bogen er ved at downloade PDF'en og søge i den.
Derved får du fremhævet ordene visuelt direkte på billedet af siden.
Digitaliseret bog
Bogens tekst er maskinlæst, så der kan være en del fejl og mangler.
Niagara Falls 100,000 Hp. Development
[45
Upon the oil switch being opened the shaft 'is turned
through an angle of 90 deg., so that the crossbar
assumes a vertical position, which releases the discon-
necting-switch compartment doors. Thus it is impos-
sible for the operator to gain access to the disconnecting
switches until the oil switch is in the open position.
Provision is made for removing the crossbar by means
of a special tool in case it is necessary for some special
reason to gain access to the “disconnects” while the oil
switch is closed.
On the reserve-bus side of the disconnecting switch
alley, where there are no oil switches, there is, of course,
no opportunity to employ this interlocking scheme; but
the six corresponding doors are fastened together
in the same manner as on the main-bus side. The
same scheme of operating the doors in groups is also
employed on the lower floor for the compartment doors,
giving access to the feeder “disconnects,” current trans-
formers and cable potheads.
Control.—As shown by
the illustrations, the control
building is placed at one
end of the series of unit
bays and parallel to them.
On the lower or ground
floor are a small office, an
entrance hall, a workshop
or store room, a storage-
battery room and a motor-
generator room, also a
longitudinal passageway
for control wiring. The
second floor is entirely oc-
cupied by the control room.
The switchboards consist
of vertical panels of natu-
ral-finished black “Linstun”
and are divided into five
sections corresponding with
the five main bays, in addi-
tion to a house-service sec-
tion. Back to back with the
control boards, with a 4-ft.
(1.2-m.) aisle between
them, are the relay and
terminal boards. A group
of five panels controls each
of the three bays connected with the new units—a bus-
tie panel, an incoming-line panel and three fender
panels, each controlling two feeders. A similar group
of four panels controls each of the other two bays. A
dummy bus indicates the connections. The bus-tie panel
is equipped with three ammeters, a wattmeter and a
reserve-bus voltmeter; the incoming-line with three am-
meters, a wattmeter, power-factor meter, main-bus
voltmeter, line voltmeter and synchroscope. Each of
the feeders is equipped with three ammeters and a
wattmeter. Each instrument and relay is provided with
a complete set of calibrating link terminals mounted
upon small panels on the rear of the main panels.
The vertical wiring on the back of the switchboards
is carried in troughs made up of two i-in. (1.9-cm.)
angle sides with “Linabestos” back, the troughs being
3| in. (8.9-cm.) wide. After the wiring was completed
these troughs were equipped with removable sheet-
metal covers. The advantages of this system of wiring
are safety, accessibility, neatness, ease of installation
FIG. 63—OXIDE-FILM LIGHTNING ARRESTERS ON INCOMING
LINES AT ECHOTA SUBSTATION
and flexibility. Furthermore, the wires being entirely
free from the panels, the latter can be easily removed,
if required, by merely disconnecting the wires from the
instruments and control devices.
At their point of departure from the board, all con-
trol wires pass through terminal links on the lower
panels of the relay boards. After leaving the switch-
board the control wires are carried in three-conductor
cables covered with flame-proof braid and laid in steel
pans or troughs mounted one above another on brackets
fastened to the wall of the building. Upon reaching the
point where the unit bays join the longitudinal passage-
way the pan for each unit passes through an opening
in the wall of the passageway and continues along the
outside wall of the bay under the oil-switch gallery.
From this pan to the current and potential transform-
ers, oil-switch controls, etc., the control wires are carried
in conduit buried in the walls and floors of the struc-
ture. By this construction
the control wiring is made
accessible throughout its
entire length, with the ex-
ception of the short por-
tion in conduit, and at the
same time an enormous
amount of conduit work is
avoided. The construction
is much less expensive and
occupies much less space
than would the conduit nec-
essary to convey an equal
number of wires. For the
operation of the control
circuits there are provided
two 14-kw. motor-genera-
tor sets and a 120-amp.-hr.,
220-volt storage battery.
The control is normally
carried on one of the motor-
generator sets and the bat-
tery held as a reserve.
Relay Protection—The
incoming lines from the
new generating station are
each equipped with over-
load, ground and reverse-
power relays. The overload
relays are arranged to trip both the main and reserve-bus
circuit breakers, but the reverse-power relays trip only
the main-bus switch. At present the reverse-power
relays are Westinghouse type CR, but it is proposed to
substitute for these type CW relays so connected as to
operate on low power factor, lagging current feeding
from the substation toward the generating station.
This is for the purpose of tripping the line switch in
case of the accidental loss of the field of the generator
and also to enable the line switch to trip on less than
full-load current in the reverse direction. The bus-tie
switch is equipped with overload relays. Feeder
switches are relayed in two different ways, according to
the nature of the feeder supplied. In certain cases where
a feeder consists of four parallel cables split-conductor
protection is provided between the twé- pairs of cables
by means of suitably connected current transformers
and low-current relays. In other cases ground relays
are installed, connected in the current-transformer
neutrals. Overload relays are also installed on all feed-