Søgning i bogen
Den bedste måde at søge i bogen er ved at downloade PDF'en og søge i den.
Derved får du fremhævet ordene visuelt direkte på billedet af siden.
Digitaliseret bog
Bogens tekst er maskinlæst, så der kan være en del fejl og mangler.
8o
HARBOUR ENGINEERING.
of wet modelling clay. The dcpth of water was 22 feet below mean low water
level, and the piles were driven by a hammer weighing about 3000 Ibs., having
a uniform effective fall of about 8 feet.
The expérimente were spread over a period of fifty-four days, when they
came to an abrupt conclusion owing to the failure of the platform under the
wash occasioned by the passage of a steamship. The last observations taken
showed the maximum settlement of any test pile to be about 31 inches, and
that the settlement of the working platform in its vicinity was If inches. It
is to be noted that this latter settlement took place under no load beyond the
weight of the piles and the timber upon them, and that, therefore, the
maximum settlement under load of any test pile was practically only lf inches.
A settlement of this amount appears to be not uncommon in local piers formed
of similar piles, even before the structure is finished, or has received any other
load than its own weight.
Mr Bensel, from various considerations indicated in his report, concludes
that the ultimate bearing power in the unlagged piles of Group I. might be
taken at 20 tons per pile, and that in the remaining groups of lagged piles the
ultimate bearing powers would be 30, 20Jand 30 tons respectively, per pile.
The following table shows details of the observations made during the
experiments. The tons are given in American units of 2000 Ibs. Roughly,
their équivalent value in English units of 2240 Ibs. may be arrived at by
deducting one-tenth. This modification applies also to the figures quoted in
the preceding paragraph.
Pile Tests at New York Harbour.
Group.
Pile.
I Diameter of point. Diameter of butt. Approximate weight of pile. I Total number of I blows to drive. Total penetration I into mud. Surface contact of pile with mud. | Average penetra- tion for eacli of last I Ave blows Load supported dur-! ing latter twenty- ! seven days of test.
ins. ins. Ibs. ft. sq. ft ins. tons.
8 18 4200 26 48 139 8 18-3
8 17 3900 19 49'6 134 9J 18-7
7 14 2700 13 50-9 127 134 18-7
61 17 3640 II 45'7 123 144 18-7
6 17 3600 46 49'6 220 4 31-8
64 15 2940 58 50-1 219 3g 31-8
74 16 3450 46 51 -0 233 4 31-8
8 164 3700 69 49’3 238 3 31'8
7 17 3700 70 50'7 247 31 28 0
8 174 4060 70 49'8 243 3J 28-0
74 184 4370 64 49'0 241 3 28-0
9 18 4450 80 499 250 21' 28-0
6 22 5700 90 52'6 257 23 28'0
74 21 5500 67 49’4 247 2f 28-0
64 22 5660 72 49'7 243 2Ï 28-0
9 19 4870 83 48'8 245 24 28-0
5 164 3270 59 507 241 38 34'6
10 184 4870 77 49-4 247 2A 34-6
74 19 4600 44 47T 231 48 34'6
7 174 3890 65 47'8 233 28 346
CO
s
ins.
i
1
«
1Ä
H
«
1*
li
11
Ir<i
1A
IH
11
li
g
g
1H
1rs
Settlement in
working platform
during same period.
Remarks.
Unlagged piles 5 ft. 6 in.
apart; in pairs, 11 ft.
6 in. apart.
Piles spaced as above
and lagged with four
5-in. x 6-in. pieces 30 ft
long.
Piles lagged as in Group
II. and arranged in
two lines of two pairs
each, tlie space be-
tween eacli line being
11 ft. 6 in.; between
the pairs in each line
5ft. 6 in. ; and between
the piles in each pair,
2 ft.8 in.
Piles spaced as in Group
II. and lagged with two
pieces 5 in.x6 in. and
two pieces 4 in. x 10 in.
all 30 ft. long.