ForsideBøgerA Treatise On The Princip… Of Harbour Engineering

A Treatise On The Principles And Practice Of Harbour Engineering

Forfatter: Brysson Cunningham

År: 1908

Forlag: Charles Griffin & Company

Sted: London

Sider: 410

UDK: Vandbygningssamlingen 134.16

With18 Plates And 220 Illustrations In The Text

Søgning i bogen

Den bedste måde at søge i bogen er ved at downloade PDF'en og søge i den.

Derved får du fremhævet ordene visuelt direkte på billedet af siden.

Download PDF

Digitaliseret bog

Bogens tekst er maskinlæst, så der kan være en del fejl og mangler.

Side af 416 Forrige Næste
BREAKWATER CONSTRUCTION. 183 10 feet by 8 feet each, set in two courses as headers and stretchers alternately. The hearting is of mass concrete. Given favourable conditions and fine weather, the superstructure could be finished during the fourth tide with the exception of the parapet wall, which was not undertaken until the full measure of settlement had been obtained. This was considered to have been achieved after the lapse of a couple of winters. From the moment a caisson was first placed to the completion of the superstructure, the settlement averaged about 8 inches. Under the load and vibration of the Titan crane setting blocks further seaward, and under the influence of winter storms, a further settlement of 16 inches took place, making 24 inches in all. When this had been realised, the joints between the caissons, which were 12 inches wide, were made good with cement concrete, and the parapet wall was built. The total amount of the contract was équivalent to £962,756, and, as the length of the breakwater is 4757 feet, the cost works out to £203 per foot run. The quantifies of material in a caisson length (42 feet 8 inches) were as follows:— Cub. yds. Cub. yds. ( Bottoin ballast 42 feet 8 inches x 23 feet x 4 feet 11 inches= 178'54 g ) Twelve blocks each 39'4 cubic yards . . . 470’88 ) Filling-in concrete ..... 180’20 O ( Steel bulkheads and tirnber struts . . . 3'55 ------833'17 Super- f Eight blocks, each 39’24 cubic yards . . 313’92 structure. 1 Filling-in concrete .... 166’77 1 --------480’69 Total . . . 1313'86 Say 1314 cubic yards in all. Breakwater at Bizerta.1—The type of structure primarily adopted at Bizerta for the converging jetties at the entrance to the port, built between 1889 and 1895, was the rubble mound, consisting of a core of pierre perdue of all sizes, surmounted and protected on the sea face by a revetment of natural blocks of large size. The site is not so exposed to violent gales as are other places on the north coast of Africa, and this system of construction was found to answer very satisfactorily. Unfortunately, the local stone (a marly limestone of poor quality, flaking rapidly in salt water) was of such a character as not to commend itself for further use, and a complété departure in design was made in dealing with the new breakwater and the extension of the north jetty, the former of which has a length of 2000 feet, and the latter of 660 feet. These works, as shown in fig. 157, were carried out by means of metallic caissons with movable upper works, forming ultimately huge artificial blocks faced with marble, which were laid upon a mass of miscellaneous riprap at a level of 26 feet below low water. The blocks measured 102 feet by 26| feet by 26| feet cubing at 70,000 feet, and having a weight of 5000 tons each. They were set with great precision, and only two blocks out of twenty-three varied perceptibly from the exact line. The settlement, averaging 27 inches, was very regular throughout. The slopes of rubble, however, intended to be 1 De Joly on Breakwaters, Min. Proc. Tenth Int. Nav. Gong. Milan, 1905. I