The Viaduct Works' Handbook
Forfatter: Henry N. Maynard
År: 1868
Forlag: E. And F. N. Spon
Sted: London
Sider: 108
UDK: 624.3
Being A Collection Of Examples From Actual Practice Of Viaducts, Bridges, Roofs, And Other Structures In Iron; Together With Tables Of Prices, Weights, And Other Information Useful To Engineers In Design And Estimating Wrought And Cast-Iron Work
Søgning i bogen
Den bedste måde at søge i bogen er ved at downloade PDF'en og søge i den.
Derved får du fremhævet ordene visuelt direkte på billedet af siden.
Digitaliseret bog
Bogens tekst er maskinlæst, så der kan være en del fejl og mangler.
at a third less than masonry, as may be seen from the following
estimates:—
COST OF AN IRON PIER.
£ S.
163 tons castings, at £13 .2110 0
7 tons wrought-iron, at £‘16 112 0
1128 yards excavation, at 1s. Cd. 84 12
1400 cube feet Ashlar masonry,
at 3s...........................210 0
42 yards concrete, at 8s. . 16 6
£2541 18
COST OF A MASONRY PIER.
£ S. d.
2197 yards excavation, at
1s.6d. . . . 164 15 6
1041 yards masonry foot-
ings, at £15s. . 1301 5 0
2120 yards, at £1 5s. . 2650 0 0
£4110 0 6
The difference in favour of iron pier, £1574 2s. 6d.
The cost of erecting, in England, structures of this kind varies
from £2 to £4 per ton.
The piers of Tagus Bridge, the superstructure of which has been
already described, at page 12, with illustrations, are an example of
the larger cylindrical piles ; in this bridge fifteen piers were required,
the average height of each pier 50 feet above the bed of the river—
a detail sketch is given at opposite page. Each pier is formed of three
cast-iron cylinders, 6 feet in diameter, 1 inch thick, made in lengths
of 6 feet, each length being built up of 4 plates or segments, planed
and turned at their junctions, so that when bolted together with
li-in. diameter bolts, and caulked with a little red lead, the joints are
made air-tight. The weight of these piers averages 25 cwt. per foot
run. The weight of bracings and bolts about 2 cwt. per foot
run. Estimating the price of the cast-iron at £8 per ton, and
wrought-iron at £16 per ton, f. o. b. an English port, it gives the
price of such a pier at £11 12s. per foot run.
The foundations of these piers, or that portion which is sunk
below the bed of the river, to an average depth of 36 feet, are
constructed by prolonging the outer piles 6 feet diameter to the
requisite depth, while the central piles, which carry a greater weight,
are increased to 8 feet diameter, to give the requisite area of bearing ‘
surface; they were sunk in the following manner :—
A sufficient number of 6-feet lengths, to reach a convenient
distance through the water, are bolted together (with thick paint
at the joints, to make them tight), and thus lowered from a raft
or temporary stage into the position required; the earth is then
removed from inside by scoops or spoons, furnished with long