A Treatise On The Principles And Practice Of Dock Engineering
Forfatter: Brysson Cunningham
År: 1904
Forlag: Charles Griffin & Company
Sted: London
Sider: 784
UDK: Vandbygningssamlingen 340.18
With 34 Folding-Plates and 468 Illustrations in the Text
Søgning i bogen
Den bedste måde at søge i bogen er ved at downloade PDF'en og søge i den.
Derved får du fremhævet ordene visuelt direkte på billedet af siden.
Digitaliseret bog
Bogens tekst er maskinlæst, så der kan være en del fejl og mangler.
COFFERDAMS.
105
On grounds of stiffness and strength, whole timber piling is preferable
to half timber piling, though a method very commonly adopted is that of
driving whole timber guide piles, with intervening bays, or panels, of half
timber piles. The guide, or king piles are provided with pointed shoes, but
the intermediate piles are shod with wedge-shaped shoes. If an edge or side
of each pile foot be splayed, the process of driving will cause it to draw
more closely to the adjoining one, and so produce continuous contact. For
the same reason it is a good plan to pitch or set a whole bay of piles and
slightly drive them all, before proceediug to a conclusion of the process with
any one of them. Furthermore, the sides of adjoining piles may be alter-
nately tongued and grooved or, alternatively, both grooved, for the reception
of a vertical strip of flat iron, say, from 2 to 3 inches wide by | inch in
thickness. The former method is of greater service for maintaining the
regularity of the piles in driving.
Skin dams need not necessarily be piled. A method very successfully
praetised at Liverpool (fig. 160) is that of constructing skin dams ashore, in
flitches of 100 lineal feet or more. They are then launched from the quay,
up-ended with the aid of a floating crane and some iron rail ballast, and
inserted in a trench previously dredged to receive them. The dam is finally
shored to the wall at uniform intervals, forming bays of from 10 to 12 feet
in length. The edges of adjoining piles are rendered a watertight joint by
menns of l-inch triangular wooden fillets nailed to the piles and closely
cramped together. Torch-wick has also been used as a watertight packing.
These flitches proved very successful and were used repeatedly, being trans-
ferred from one site to another as occasion required. A length of over 4,500
feet of dock walls was underpinned in this manner. The cost of the flitches,
including maintenance and removal, varied between £13 and £18 per lineal
foot.
A skin dam has been made self-supporting by constructing it in the
form of a bottomless box for work which could be carried on in the interior.
The outer faces then afford one another mutual support through the medium
of cross shores and struts. The method as applied to the construction of a
dock wall at Liverpool is shown in fig. 133. It will be noticed that the
outer sheeting consists of a series of horizontal timbers, ranging in thickness
from 12 inches at the bottom to 3 inches at the top. Water-tightness is
effected by means of torch-wick joints. Inside the sheeting there is a
continuous row of piles driven down to a rock substratum, and acting as a
support for an overhead crane road. The dam in question was 246 feet long,
in lö-foot bays. The cost was rather less than £35 per foot run.
In all cases the foot of a skin dam has to be amply protected and covered
by a thick layer of clay puddle, which will need replenishing from time to
time as the clay subsides.
Cofferdams consist essentially of two timber faces enclosing a hearting,
generally of clay (fig. 66), but occasionally of stone. They are of more solid
construction than skin dams, but, at the same time, they offer some risks of