A Treatise On The Principles And Practice Of Dock Engineering
Forfatter: Brysson Cunningham
År: 1904
Forlag: Charles Griffin & Company
Sted: London
Sider: 784
UDK: Vandbygningssamlingen 340.18
With 34 Folding-Plates and 468 Illustrations in the Text
Søgning i bogen
Den bedste måde at søge i bogen er ved at downloade PDF'en og søge i den.
Derved får du fremhævet ordene visuelt direkte på billedet af siden.
Digitaliseret bog
Bogens tekst er maskinlæst, så der kan være en del fejl og mangler.
CONSTRUCTION IN PNEUMATIC CHAMBERS.
201
clear of all mud and silt before berthing the dam. A good supply of clay
will be necessary to replace wastage in the puddle.
The length of the dam in question was 246 feet, divided into 16 bays
of 15 feet each, with an overlap at one end. On the conclusion of the
work the piles were drawn, and the sides of the dam removed separately.
In a similar manner the concrete walls of a tidal basin at Ardrossan were
constructed.* Fig 134 is a section of the wall and of the box dam within
which it was built.
Construction in Pneumatic Chambers.—This system, in one or other of
its forms, represents a very considerable proportion of Continental practice,
but it does not seem to have been adopted in any noteworthy instance in
English ports, if, as is intended, we
restrict the use of the diving bell to
the actual construction of the wall.
The system dates back some considér-
able time, and walls have been con-
structed on its principles, notably at
Antwerp, Marseiiles, Genoa, and else-
where.
The following account of its appli-
cation to the recently constructed quay
walls of the Bassin de la Pinède, at
Marseilles, is extracted and condensed
from an article by M. Batard-Razeliére,
Engineer - in - Chief of the harbour
■works there :—t
“ The foundation of the quay walls
is laid on stiff ground (ballast, grit, or
hard clay), when that ground is met
with above a level of 40 feet below
Fitting
2'5"
Mud
Firm 'tiroujid
Fig. 135. —Dock Wall at Marseilles—
Section A.
- - 42' 0
Batter 1 in. 20
the datum of ordinary low-water level. The profile of the wall is then
represented by fig. 135. The masonry is bedded into the ground for a width
of about 10 feet at its base. When stiff ground is only to be found below
the above-named level, the site is dredged to that depth, the material con-
sisting mainly of mud, sand, and decayed seaweed. A bank of rubble
stone is then formed and brought up to a level of 30 feet below datum,
having at this level a width of 41 feet, and the normal section of the wall
is founded upon this base, as in fig. 136.
To within 5 feet of low-water level the work is executed, by means of
compressed air, in the interior of large metallic chambers (caissons J), acting
like diving bells. From 5 feet below to 18 inches above datum it is
* Robertson on “Ardrossan Harbour Extensions,” Min. Pruc. Inst. C.E., vol. cxx.
+ Bulletin de la Société Scientifique Industrielle de Marseille, 2me Trimestre, 1900.
t The word “ caisson” in this connection has not quite the signification which it
has when applied to the apparatus for closing a dock entranee.