A Treatise On The Principles And Practice Of Dock Engineering
Forfatter: Brysson Cunningham
År: 1904
Forlag: Charles Griffin & Company
Sted: London
Sider: 784
UDK: Vandbygningssamlingen 340.18
With 34 Folding-Plates and 468 Illustrations in the Text
Søgning i bogen
Den bedste måde at søge i bogen er ved at downloade PDF'en og søge i den.
Derved får du fremhævet ordene visuelt direkte på billedet af siden.
Digitaliseret bog
Bogens tekst er maskinlæst, så der kan være en del fejl og mangler.
204
DOCK ENGINEERING.
The total weight of a caisson is, on an average, nearly 410 tons, including
350 tons of kentledge. This weight is reduced to about 290 tons when the
caisson is immersed, and to 30 tons when it is sunk and the working
chamber full of air.
Having dredged and prepared the site, as before deseribed, the caisson is
conducted to its place between two barges connected by a framing which
forms a deck above the caisson. The latter is then lowered into position and
detached from its supports. The working chamber having been filled with
compressed air, the surface of the ground uncovered is cleared and levelled,
and a block of masonry built upon it about 4 feet in height, its other
dimensions corresponding to the size of the chamber and the width of the
wall, with a slight clearance in the former case. This completed, the caisson
is removed to an adjoining site by a reversal and renewal of the process, the
blocks being constructed as closely together as possible and leaving only an
interval of about 3 feet between them. A second caisson following the first
builds the second course, and at the same time by sitting over the joints
between the blocks fills up the vacant spaces with the aid of a diver, who
rapidly constructs a brick wall, back and front of the spaces, which are then
pumped dry and filled with masonry.
The fifth caisson is self-acting ; it can sink or float by its own appliances.
It is larger and heavier than the others, and is intended to be worked at
variable depths, being used principally for constructing the bottom course of
blocks. Its functions generally, however, are the same as those of the other
four chambers.
Ordinarily, no excavations were made within the caissons except
such as were necessary to prépare a level seat for the wall; in certain
cases, however, it was possible to descend about 6 feet below the initial
position of the chamber, but there would have been risk in sinking
lower, on account of the possibility of not being able to liberate the
caisson.
Where firm earth is met with above the floor of the basin, which is the
case along and in the neighbourhood of the landward side, the wall is only
built to its full width above that level. The lower portion of the wall is
simply constructed as a retaining wall or revetment of about 5 feet in thick-
ness, as shown in fig. 139. In this case the caisson is sunk to rest upon the
higher level, and the firm stratum below being practically impermeable, the
revetment is put in by means of a trench, and the upper portion of the wall
is proceeded with as usual.
The rate of working has depended on the nature of the foundation; in
the case of very hard ground requiring the pick, the rate of descent of the
caisson did not exceed 6 inches per day of 24 hours. In the building of
the wall each mason executes about 88 cubic feet of masonry in a shift of
eight hours. The construction of one block of masonry absorbed three
days, including the manipulation of the caisson and the making good of
the joint in the course below. The cost of the masonry, exclusive of the