A Treatise On The Principles And Practice Of Dock Engineering
Forfatter: Brysson Cunningham
År: 1904
Forlag: Charles Griffin & Company
Sted: London
Sider: 784
UDK: Vandbygningssamlingen 340.18
With 34 Folding-Plates and 468 Illustrations in the Text
Søgning i bogen
Den bedste måde at søge i bogen er ved at downloade PDF'en og søge i den.
Derved får du fremhævet ordene visuelt direkte på billedet af siden.
Digitaliseret bog
Bogens tekst er maskinlæst, så der kan være en del fejl og mangler.
2o8
DOCK ENGINEERING.
piles are cut off to the desired height and fitted with iron collars to support
the cross beanis, 9 to 12 inches square, which, in turn, carry the flooring,
4 inches thick. Two consecutive lengths of platform are prepared in this
way, and then the caisson is berthed over the interval between theni, and
the decking made continuons. In one week, 14 men working within the
pneuraatic chamber can completely prepare a length of more than 22 yards
of platform.
Upon the foundation thus constructed, the wall is built to its full height
with concrete blocks, 8 feet long, 3 feet high, and as wide as the wall is
thick, having a facing of basalt. Brickwork has been tried, with unsatis-
factory results.
The fascine work is made good between the beams to the underside of
the decking, and an additional mattrass is sunk behind the timber work so
as to present an upper surface level with the planking. Finally, a mattrass
is laid partly upon the platform and partly upon the fascine work behind,
and the whole is filled with sand.
A lineal yard of wall constructed in this manner costs at the present day
900 florins, of which one-third may be assigned to the fascine mattrass work.
Fig. 113 shows a cross section of the completed wall.
Construction with Monolithic Blocks.—By this system, which consists in
building the submerged portion of a quay wall in a series of massive blocks,
the use of cofferdams is avoided, and also that of diving bells, except in so
far as the latter are found necessary for providing a suitable and level
foundation for the blocks. The blocks themselves may be set by means of a
floating crane or sheers, and accurately adjusted with the assistance of a
diver, who may also, under favourable circumstances, be able to prepare the
site for their reception.
Perhaps the most notable instance of the adoption of this method is to be
found at Dublin, where the quay walls have a monolithic base course,
27 feet in height, reaching to 3 feet above equinoctial low water. The
width of each block at the base is 21 feet 4 inches, forming the entire
thickness of the wall ; the face length is 12 feet, and the total contents are
nearly 5,000 cubic feet of masonry, weighing 350 tons. Adjacent blocks
are connected by means of dowels, formed by filling with concrete long
vertical grooves, 3 feet square in plan, one-half of which is arranged in the
side of each block.
The following particulars relate to the quay wall of a tidal basin built,
in 1871,* under the direction of Dr. Stoney, F.R.S., the engineer to the
Port Trust.
The necessary préparation and levelling of site were effected by the
agency of a diving bell, covering an area of 400 square feet, and furnished
with a shaft, 3 feet in diameter, rising from its roof above the surface level
of the water, where it was connected to an air-lock for the passage of men
* Stoney on “ The Construction of Harbour and Marine Works with Artificial Blocks
of Large Size,” Min. Proc. Inst. C.E., vol. xxxvii.