A Treatise On The Principles And Practice Of Dock Engineering
Forfatter: Brysson Cunningham
År: 1904
Forlag: Charles Griffin & Company
Sted: London
Sider: 784
UDK: Vandbygningssamlingen 340.18
With 34 Folding-Plates and 468 Illustrations in the Text
Søgning i bogen
Den bedste måde at søge i bogen er ved at downloade PDF'en og søge i den.
Derved får du fremhævet ordene visuelt direkte på billedet af siden.
Digitaliseret bog
Bogens tekst er maskinlæst, så der kan være en del fejl og mangler.
266 DOCK ENGINEERING.
inserted and other preventive steps taken. Pumping was reduced to the
minimum necessary for getting in a piled foundation for the side walls at
the highest possible level. The holes were filled with chalk rubble and the
wliole area covered with it in order to intercept the flow of silt. Bearing
piles were then driven between a network of temporary timbering, connected
at the top by whole timber caps and covered with a double thickness of elm
planking. As regards the origin of the water in the blows, investigations
seemed to indicate the existence of parallel water-courses below the bed of
clay running transversely to the lock.
The principal difficulty being anticipated at the inner gate platform, it
was proposed to excavate the foundation in small areas, enclosed by half
timber sheeting, grooved and tongued, but after a few piles had been driven
some blows occurred at the surface, which was a little above dock bottom,
and water came up in considérable quantities. Large holes formed, and some
of the sheeting disappeared. Cast-iron pipes were driven vertically into the
two principal springs, and in one of these the water reached a height of
14 feet above dock bottom. Several hundred yards of clay puddle were
absorbed by one hole alone. To reach the origin of the disturbance it was
clearly necessary to carry the sheeting lower down, and accordingly pitch
pine piles, 14 inches square and 50 feet long, grooved and tongued, were
driven so as to enclose the disturbed area and eut off the flow of water,
which was effectively done and the foundations completed. The roller
path stones and sills were laid on elm platforms over bearing piles. The
discharge through one of the blowhole pipes was stopped, but the water
continued to flow through the other until the pipe was closed at the
completion of the works.
New Lock at Bremerhaven.
This lock (fig. 206) has an efficient length of 656 feet, or a length of
705 feet between gates. The breadtli of the entrance is 92 feet, and of the
chamber 147 feet, so that the largest passenger steamers can lie there
preparatory to starting and receive cargo from lighters. The depth is
sufficient to accommodate ships drawing 31 feet during neap tides. An