ForsideBøgerA Treatise On The Princip…ice Of Dock Engineering

A Treatise On The Principles And Practice Of Dock Engineering

Forfatter: Brysson Cunningham

År: 1904

Forlag: Charles Griffin & Company

Sted: London

Sider: 784

UDK: Vandbygningssamlingen 340.18

With 34 Folding-Plates and 468 Illustrations in the Text

Søgning i bogen

Den bedste måde at søge i bogen er ved at downloade PDF'en og søge i den.

Derved får du fremhævet ordene visuelt direkte på billedet af siden.

Download PDF

Digitaliseret bog

Bogens tekst er maskinlæst, så der kan være en del fejl og mangler.

Side af 784 Forrige Næste
266 DOCK ENGINEERING. inserted and other préventive steps taken. Pumping was reduced to the minimum necessary for getting in a piled foundation for the side walls at the highest possible level. The holes were filled with chalk rubble and the whole area covered with it in order to intercept the flow of silt. Bearing piles were then driven between a network of temporary timbering, connected at the top by whole timber caps and covered with a double thickness of elm planking. As regards the origin of the water in the blows, investigations seemed to indicate the existence of parallel water-courses below the bed of clay running transversely to the lock. The principal difficulty being anticipated at the inner gate platform, it was proposed to excavate the foundation in small areas, enclosed by half timber sheeting, grooved and tongued, but after a few piles had been driven some blows occurred at the surface, which was a little above dock bottom, and water came up in considérable quantities. Large holes formed, and some of the sheeting disappeared. Cast-iron pipes were driven vertically into the two principal springs, and in one of these the water reached a height of 14 feet above dock bottom. Several hundred yards of clay puddle were absorbed by one hole alone. To reach the origin of the disturbance it was clearly necessary to carry the sheeting lower down, and accordingly pitch pine piles, 14 inches square and 50 feet long, grooved and tongued, were driven so as to enclose the disturbed area and cut off the flow of water, which was effectively done and the foundations completed. The roller patli stones and sills were laid on elm platforms over bearing piles. The discharge through one of the blowhole pipes was stopped, but the water continued to flow through the other until the pipe was closed at the completion of the works. New Lock at Bremerhaven. This lock (fig. 206) has an efficient length of 656 feet, or a length of 705 feet between gates. The breadth of the entrance is 92 feet, and of the Fig. 206. —Bremerhaven Lock. chamber 147 feet, so that the largest passenger steamers can lie there preparatory to starting and receive cargo from lighters. The depth is sufficient to accommodate ships drawing 31 feet during neap tides. An